Permit Information
Permit NumberESC13-00524
StatusFinaled
Name BOB BERRYMAN
Site Address 4441 N BOGUS BASIN RD
Project NameHackberry Ranch Subdivision
Customer Number 
ePlanReviewNo
Description
Hillside subdivision development. CGP coverage for site owner under # IDR12CU20. Central paving has already put in roads and infrastructure with some work remaining as January 2014
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Site Final8/1/20198/1/20198/2/2019PPASS
DetailsAndy J. Long
Open areas vegetated. All work complete. Only se several open lots left. 1 active home under construction, permited seperately.

No further ESC requests. Permit finaled.
General Inspection8/1/20198/1/20198/1/2019 CANC
DetailsAndy J. Long
General Inspection7/1/20197/1/20197/1/2019 PASS
DetailsMichael Zawacki
No orhood. One new home has begun construction, in good standing and has active permit.
General Inspection5/30/20195/30/20195/30/2019 PASS
DetailsMichael Zawacki
Old witches hat still installed at PasoFino and mountainside. Growth on all vacant lots and hillside at top of neighborhood.
General Inspection4/29/20194/29/20194/29/2019 CANC
DetailsAndy J. Long
General Inspection3/28/20193/28/20193/29/2019 PASS
DetailsMichael Zawacki
No new construction activity. No slope failures.
General Inspection2/25/20192/25/20192/26/2019 PASS
DetailsMichael Zawacki
Few vacant lots, no slope failures on upper end. Will monitor until stabalized.
General Inspection1/24/20191/24/20191/24/2019 PASS
DetailsMichael Zawacki
Few lots remain. No failures over winter. Hill on top of site still has very sparse vegetation.
General Inspection12/24/201812/24/201812/24/2018 CANC
DetailsAndy J. Long
General Inspection11/22/201811/22/201811/23/2018 PASS
DetailsAndy J. Long
General Inspection10/22/201810/22/201810/22/2018 PASS
DetailsAndy J. Long
No new activity. WIll keep open to monitor the sparsely vegetated slope above Paso Fino. Some areas are bare, others have low lying vegetation. Slope interupting wattles are installed and are decomposing. No rills or sediment runof observed to street
General Inspection9/20/20189/20/20189/21/2018 PASS
DetailsAndy J. Long
General Inspection8/20/20188/20/20188/20/2018 PASS
DetailsAndy J. Long
General Inspection7/19/20187/19/20187/23/2018 PASS
DetailsMichael Zawacki
Few lots still unbuilt. No current activities.
General Inspection6/18/20186/18/20186/18/2018 PASS
DetailsMichael Zawacki
Few vacant lots. All lots are now overgrown with weeds and grasses and are stable. No ESC issues at site.
General Inspection5/17/20185/17/20185/21/2018PPASS
DetailsAndy J. Long
post rainfall
General Inspection5/7/20185/7/20185/7/2018 PASS
DetailsMichael Zawacki
Parcel on corner of Paso Fino & Mountainview has sold, major contributor to runoff.
Neighborhood is mostly complete and stable. One lot noted above is only one with any issues.
General Inspection4/5/20184/5/20184/5/2018 PASS
DetailsMichael Zawacki
Few vacant lots. Runoff from first lot on right to storm drain at Paso Fino and Mountainside. Witches hat is full on drain. Only the one lot is having any issue.
General Inspection3/5/20183/5/20183/5/2018 CANC
DetailsAndy J. Long
General Inspection2/1/20182/1/20182/1/2018 PASS
DetailsAndy J. Long
General Inspection1/1/20181/1/20181/2/2018 PASS
DetailsMichael Zawacki
Few vacant lots remain. No issues with runoff from melting snow.
General Inspection11/30/201711/30/201711/30/2017 PEND
DetailsMichael Zawacki
Few vacant lots remain. Water and sediment running onto Paso Fino from vacan lots. Very bad from lot on corner od Paso Fino & Mountainside.
General Inspection10/30/201710/30/201710/30/2017 CANC
DetailsAndy J. Long
General Inspection9/26/20179/29/20179/29/2017APASS
DetailsAndy J. Long
General Inspection9/25/20179/25/20179/26/2017 CANC
DetailsAndy J. Long
Conference8/18/20178/23/20178/22/2017ACANC
DetailsAndy J. Long
General Inspection8/17/20178/17/20178/18/2017 CANC
DetailsAndy J. Long
General Inspection7/17/20177/17/20177/18/2017 PEND
DetailsMelissa Jannusch
Utility trenching in progress. Area where the dirt from the trenching is located needs to be swept up after the trenches are backfilled.
No dust. No trackout. Trash is contained.
General Inspection6/15/20176/15/20176/16/2017 PART
DetailsMelissa Jannusch
Small amount of trackout in parking areas. The entrance needs to be redone as the new road goes in.
General Inspection5/15/20175/15/20175/15/2017 PASS
DetailsAndy J. Long
Hillsides vegetation in good condition. Most lots in Hackberry Ranch and now built upon. One active home under construction. Temporary DI sediment filter bags are still installed.
General Inspection4/13/20174/13/20174/13/2017PPASS
DetailsMelissa Jannusch
Vegetation on hillsides is growing well. No corrections.
General Inspection3/23/20173/23/20173/23/2017 CANC
DetailsAndy J. Long
General Inspection2/20/20172/20/20172/21/2017 CANC
DetailsMelissa Jannusch
Holiday
General Inspection1/19/20171/19/20171/23/2017 CANC
DetailsAndy J. Long
General Inspection12/19/201612/19/201612/21/2016 CANC
DetailsAndy J. Long
General Inspection11/17/201611/17/201611/17/2016 PASS
DetailsAndy J. Long
No hillside erosion issues observed in common areas. Individual SFHs have seperate ESC permits . No activity yet on next phase across Bogus Basin Road. No corrections at this time.
General Inspection10/17/201610/17/201610/17/2016 CANC
DetailsAndy J. Long
General Inspection9/15/20169/16/20169/19/2016APASS
DetailsAndy J. Long
Slopes are in good condition and appear to be stable. Two SFHs with seperate ESC permits are in progress. BMPs installed. Will close this permit when application/permit for phase across Bogus Basin Road is issued.
General Inspection9/15/20169/15/20169/15/2016 CANC
DetailsAndy J. Long
rescheduled 9/16
General Inspection8/15/20168/15/20168/15/2016 PASS
DetailsEvan Jenkins
No ESC issues observed at this time
General Inspection7/15/20167/15/20167/15/2016 PASS
DetailsEvan Jenkins
1 SFH in progress and near completion. No ESC issues observed
Random Inspection6/14/20166/14/20166/14/2016PPASS
DetailsEvan Jenkins
General Inspection5/26/20165/26/20165/26/2016 CANC
DetailsAndy J. Long
General Inspection4/25/20164/25/20164/26/2016 CANC
DetailsAndy J. Long
General Inspection3/24/20163/24/20163/24/2016 PASS
DetailsEvan Jenkins
Only 1 SFH under construction. No discharges or trackout occuring at this time
General Inspection2/22/20162/22/20162/22/2016 PASS
DetailsAndy J. Long
General Inspection1/21/20161/21/20161/21/2016 PASS
DetailsAndy J. Long
SFHs in progress at Hackberry Ranch. Seeded hillsides appear to be stabile, no erosion rills or gullies observed in common areas or from individual parcels.

Inlets have filter bags installed. Will continue to inspect as subdivision becomes fully occupied and revegetated. No corrections at this time.
General Inspection12/21/201512/21/201512/21/2015 PASS
DetailsEvan Jenkins
General Inspection11/19/201511/19/201511/19/2015 PASS
DetailsAndy J. Long
No erosion or sediment runoff occuring on Hackberry Ranch slopes. Streets, sidewalks and gutters are free of loose dirt and trackout. Only 1 active SFH in progress. Site monitoring or revegetation and SFH construction will continue. Discussed hillsides and seeding applications with project owner Scott Kimball on site.

No corrections at this time.
General Inspection10/19/201510/19/201510/19/2015 PASS
DetailsEvan Jenkins
Vacant lots have no discharge coming off as of time of inspection. WIP on multiple SFD's throughout Hackberry Sub.
General Inspection9/18/20159/18/20159/18/2015 PASS
DetailsEvan Jenkins
SFH work in progress on several homes. No trackout observed or other ESC issues observed.
General Inspection8/14/20158/18/20158/18/2015PPASS
DetailsAndy J. Long
No hillside erosion on Hackberry Ranch slopes. Streets and gutters are free of trackout and sediment accumulations. Individual homes have been keeping in compliance and have BMPs installed. No corrections issued.
General Inspection8/10/20158/10/20158/14/2015 CANC
DetailsAndy J. Long
rescheduled 8/18
General Inspection7/9/20157/9/20157/9/2015 PART
DetailsEvan Jenkins
Some discharge into Mountain Side Rd due to a house at end of culdesac. Rain gutters aren't hooked up into the MS4, so that's where the erosion came from.
Correction:
1.) Sweep Mountain Side
2.) Hook Gutters into MS4 System to reduce future chances of Erosion
General Inspection6/8/20156/8/20156/8/2015 PASS
DetailsEvan Jenkins
The New Phase II (below this project/permit) has been prepped for residential lots. No work occuring the past 2 weeks. No ESC issues at this time.
General Inspection5/8/20155/8/20155/8/2015 PASS
DetailsEvan Jenkins
General Inspection4/7/20154/7/20154/7/2015PPASS
DetailsAndy J. Long
Hillside slopes in Hackberry have been recently hydroseeded/tacified. The drainage channel along Bogus Basin was also hydroseeded. Coverage looks good. No hillside erosion or areas of significant sediment runoff. Permit open to monitor stabilization of hillsides.
General Inspection3/12/20153/12/20153/12/2015 PASS
DetailsEvan Jenkins
Roads have been swept lately. Vegetation is growing well, where there is no "New" disturbance.
No ESC issues at this time
General Inspection2/9/20152/9/20152/9/2015 PEND
DetailsAndy J. Long
Corrections:

1. Need to reseed some areas on the upper side of Paso Fino.
2. Need to have builders or grounds crew pick up litter and materials that have blown off sites.
3. Need to check all DI bags and stormdrains for dirt/sediment accumulation. Found about half of the bags on inlets are full of dirt.

Email developer; will work with individual builders to make corrections as well.

Hackberry Ranch is mostly stable, just need to do some BMP maintenance and make sure the storm drainage system does not get clogged up with sedment.


General Inspection1/8/20151/8/20151/8/2015 PASS
DetailsAndy J. Long
No hillside erosion issues in the seeded areas. Limited trackout to streets, significant amounts of sand in road from winter driving safety applications.

Individual SFHs in progress with permits posted. Drop inlets protected and no issues within the stormwater retention/infiltration ponds. No corrections at this time. Will continue to monitor.
General Inspection12/8/201412/8/201412/8/2014 PASS
DetailsEvan Jenkins
General Inspection11/6/201411/6/201411/6/2014 PASS
DetailsEvan Jenkins
Overall site looks good. Some minor rilling occuring, but vegetation is quickly growing, so root structures should address that issue. some minor trackout occuring, but 2 people are currently hand sweeping and performing maintenance on drop inlet bags.
General Inspection10/6/201410/6/201410/6/2014 PASS
DetailsAndy J. Long
Hackberry Ranch hillsides, drainage structures, and streets currently have no ESC issues. Work on going on multiple SFHs, each with their own permit.

Next inspection will check downstream check dams for maintenance needs. Drainage channel next to Bogus Basin Road is vegetating well, which will help dissipate stormwater flows and hold sediment in place..
Random Inspection9/3/20149/3/20149/3/2014APASS
DetailsAndy J. Long
Hillside gullies have been repaired and roads, gutters, and DI bags have been maintained to remove accumulated sediment. No new issues or areas of concern at this time. Need to continue to monitor check dams in the drainage below the site.
General Inspection8/14/20148/15/20148/15/2014APASS
DetailsAndy J. Long
Hackberry Ranch follow up inspection

Crew onsite has nearly completed all sweeping.
Stormdrain drop inlet filter bags have been emptied and reinstalled.

An additional sediment containment BMPs will be installed at top of Mountainside.

Talked to developer Scott Kimball who is managing the SWPPP and corrective actions currently.

Approved.
General Inspection8/14/20148/14/20148/14/2014ACANC
DetailsAndy J. Long
Random Inspection8/14/20148/14/20148/14/2014PPART
DetailsAndy J. Long
Previous day's thunderstorm created some erosion and sediment runoff into streets and stormdrains.

Crew onsite sweep and remove accumulated sediment at time of inspection.

Corrections:
1. Clean up sediment; maintain inlet protection, repare areas of rill erosion.
2. Need increased stabilization and sediment containment at top of Mountainside (4958 Mountainside -undeveloped)

Will check progress tomorrow.
General Inspection7/24/20147/24/20147/24/2014 PASS
DetailsAndy J. Long
No further subdivision development at Hackberry Ranch. Hills have vegetated well but will need to reassess success level during the fall. Central Paving has closed their CGP for the project, and the Hackberry Ranch Corp has left their's open to monitor final stabilization.

No correction required. Individual homes are in progress by multiple contractors and are currently in compliance and keeping it clean and using BMPs.
General Inspection6/23/20146/23/20146/23/2014 PASS
DetailsEvan Jenkins
80% re-vegetation almost achieved
No ESC Issues
Site Final5/23/20145/23/20145/23/2014PPART
DetailsEvan Jenkins
Garry Phone #: ###-####
Per Hillside Requirements and The City's 8-17 Ordinance, 80% of native background vegetation needs to be established prior to this permit through the city to be closed.
The 2012 Construction General Permit allows a contractor/developer 3 yrs to achieve 70% re-establishment. I do not see an issue with the Developer to File their "Notice of Termination" with the EPA, but the City's Permit will remain open until 80% vegetation re-establishment is acheived throughout the entire site. It is very close to achieving this requirement.
No ESC Issues observed during inspection. Vegetation is growing well. Some areas are still baren. Could use another Hydroseeding application
Random Inspection5/9/20145/9/20145/9/2014PPASS
DetailsAndy J. Long
Hackberry Ranch subdivision construction is indicated to be in "Completed Phase". RP Bob Berryman is continuing to inspect stormwater ponds and structures. Last SWPPP inspection logged in book was 4/28/14 and they are on a 2 week schedule unless it rains. It is raining today, and possilbly over .25". No corrections. Hillsides revegetating well.
Random Inspection4/18/20144/18/20144/18/2014PPASS
DetailsAndy J. Long
Hackberry Ranch looking good up top. Central Paving is onsite on the lower drainage improving checkdams and has installed additional wattles in channel to slow runoff speed. Final check dam is to be converted to 1:1 rock water fall with a rip rap channel constructed all the way to the lower pond. No corrections at this time.
Random Inspection4/3/20144/3/20144/3/2014PPASS
DetailsAndy J. Long
Hillside inspection of Hackberry Ranch.

No violations observed. Hillside vegetation is growing most areas. No trackout. The WR Gann project (lot 10) has not been worked on since SWO.
Random Inspection3/18/20143/18/20143/18/2014PPASS
DetailsAndy J. Long
Hackberry Ranch looks good. No sediment on roadways. Grass is starting to grow in seeded areas, all stabilization has been initiated. No violations observed.

Lower drainage channel with rill/channel erosion will be repaired after this spring.
Random Inspection3/10/20143/10/20143/10/2014PPASS
DetailsAndy J. Long
Hillside vegetation is starting to establish in multiple areas. Previous corrections to rill erosion are holding together. Streets clean. Downstream drainage will need repair this spring, but development area is looking good through rain currently.
General Inspection2/18/20142/18/20142/18/2014PFAIL
DetailsEvan Jenkins
SIgnificant sediment let a few of the lots throughout the project, discharging sediment over the sidewalks, curbs and streets. Drop Inlets need to be replaced/cleaned out. Rills and Gully Erosion taking place throughout entire site that need to be focussed on (filling in, compacting). Talked with Bob (RP), he stated he is unable to get any of his crew onsite today unfortunately, due to no precipitation and the grounds are relatively dry. He stated he was not able to sweep roads due to the rainfall, but will as soon as he can. He stated he will contact me via cell to discuss progress
BMP Violation2/13/20142/13/20142/13/2014APEND
DetailsAndy J. Long
Initial corrections discussed during conference 2/12 that were able to be completed without accessing muddy lots/hillside with equipment.

Roads were blowouts occured were scraped and cleaned. Some dirt remaining but will be swept as is dries. DI bags that were full were emptied. Upper main drainage inlet was provided with gravel check dams and wattles staked down. Lower rill erosion filled with rock drips to stabilize.

Will continue to monitor as conditions improved for further corrections. Hydroseeding is scheduled to occur next week on areas that are not yet stabilized.

Initial response by contractor is good, but more work needs to be done for full compliance.
Conference2/12/20142/12/20142/12/2014PDONE
DetailsAndy J. Long
Co nference called due to need for correctiions and maintenance of BMPs. Snowmelt, rainfall, and the ground thawing has created multiple ESC issues.

RP Bob Berryman of Central Paving and Doug Powell, the site engineer met me onsite to discuss corrections.

1. Channel erosion below final check dam will have banks regraded and length of riprap extended. Working with PW engineers Jim Wylie on these corrections.

2. Blowouts onto roads will be cleaned.
3. Additional check dams to be installed at lower intersection problem area.
4. Drainage protection to be enhanced on upper drain on main subdivision road.

Central Paving started on corrections at end of conference. Dave Powell will be onsite daily this week to supervise.

Hydroseeding/mulching on remaining areas is scheduled for next week.

Will check back 2/13 to monitor progress.
Random Inspection2/11/20142/11/20142/11/2014PFAIL
DetailsAndy J. Long
Central Pavement on-site making corrections at time of inspection. Rill erosion and sediment loading onto streets within Hackberry Ranch. Water is pooling on flat area but does not infiltrate quickly enough to reduce pressure on earthen berms which created some blow outs.

Recommended placing gravel check dams at openings to berms and laying down straw to reduce impact of rain and slow down runoff.
Random Inspection1/30/20141/30/20141/30/2014PPASS
DetailsAndy J. Long
BMPs performed well through the 1/29 precipitation event. No new rills/channels formed. Earthen berms installed on flat lots were effective.

Roads in good condition with no trackout.

Approved.
BMP Violation1/21/20141/21/20141/21/2014PPEND
DetailsAndy J. Long
RP Bob Berryman called to inform that corrections have been made at Hackberry Ranch from last weeks CN. Follow up inspection.

Corrections were addressed. Areas of rill erosion were filled in and additional berms and wattles were installed. Wattles also repaired at top of road with long slope. SWPPP inspection was also completed.

Bob Berryman reviewed schedule. Sweeping on Bogus will be conducted by end of week. County inspections next week for water lines and stormwater system and neighborhood streets will be swept. Hydroseeding to be completed in first two weeks of February.

No further corrections for now, just need to sweep up and also make landscaping crews do daily cleaning.
Complaint Inspection1/16/20141/16/20141/16/2014PPART
DetailsAndy J. Long
PW Jim Wylie commented on some rill erosion. Need to check it out.

Inspection conducted by Evan and myself. Hillside rilling evident in some areas, some wattles failed during snowmelt.
, considering size and scope many BMPs were effective.

Talked to Central Paving RP Bob Berryman and issued following corrections:

1. Need to conduct SWPPP inspections and update construction schedule/project status.
2. Repair damaged/untrenched wattles as necessary.
3. Address several slope areas between graded flat lots where rill erosion is evident. i.e. repair containment berms, place rip rap to guide, or other applicable BMP
4. Finish hydroseeding schedules where no further work/disturbance is scheduled.

note: developer Scott Kimball was also notified.
General Inspection1/10/20141/10/20141/10/2014 PASS
DetailsAndy J. Long
No construction activity at time of inspection. BMPs and hillside stabilization appears to be adequate dispite significant snow melt runnoff over past 2 days. No dirt or sediment blowouts onto roads. No corrections at this time.
General Inspection12/10/201312/10/201312/10/2013 PASS
DetailsAndy J. Long
No activity at time of inspection. Roads have been paved. New stormwater facilities have inlet protection. Hillsides are tracked horizontally and wattles installed incrementally on hillsides. No corrections required.
Tracking Control11/8/201311/8/201311/8/2013PPASS
DetailsAndy J. Long
Construction entrance was replenished as requested. Finishing work on stormwater infrastructure connection to downstream pond with active construction in the right of way. No further corrections.
Random Inspection11/7/201311/7/201311/7/2013APART
DetailsAndy J. Long
Hillsides have been stabilized with hydroseed/mulch; wattles are installed. No hillside erosion issues observed. Need to replenish construction entrances as they have been compacted into the mud. Called RP Bob Berryman with Central Paving to make correction. Will reinspect early next week
General Inspection10/23/201310/23/201310/23/2013 PASS
DetailsAndy J. Long
BMPs installed. No corrections at this time.
General Inspection9/19/20139/19/20139/20/2013 PASS
DetailsBill VanDegrift
General Inspection8/8/20138/8/20138/9/2013 CANC
DetailsKimberly M. Johnson
Complaint Inspection7/8/20137/8/20137/8/2013PPASS
DetailsKimberly M. Johnson
dust complaint. No dust at time of inspection. Contacted Dave Powell (RP) to notify.