General Inspection | 8/7/2020 | 8/7/2020 | 8/7/2020 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 7/23/2020 | 7/23/2020 | 7/23/2020 | | CANC |
Andy J. Long
|
|
|
open per request of parks n rec. No activity currently
|
Site Final | 7/6/2020 | 7/8/2020 | 7/9/2020 | P | NR |
Andy J. Long
|
|
|
check with Kelly on status
More work on second wave may need to occur. Need to remove silt fence and the far west end of project near VMP ramp and greenbelt.
|
General Inspection | 7/3/2020 | 7/3/2020 | 7/6/2020 | | CANC |
Andy J. Long
|
|
|
rescheduled for site final
|
General Inspection | 6/18/2020 | 6/18/2020 | 6/18/2020 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 6/3/2020 | 6/3/2020 | 6/8/2020 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 5/19/2020 | 5/19/2020 | 5/19/2020 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 5/4/2020 | 5/4/2020 | 5/4/2020 | | PASS |
Michael Zawacki
|
|
|
Site has good vegetation growth. Under care of parks dept. No disturbances in main park area.
|
General Inspection | 4/17/2020 | 4/17/2020 | 4/17/2020 | | CANC |
Michael Zawacki
|
|
|
|
General Inspection | 4/2/2020 | 4/2/2020 | 4/2/2020 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 3/18/2020 | 3/18/2020 | 3/18/2020 | | CANC |
Michael Zawacki
|
|
|
|
General Inspection | 3/3/2020 | 3/3/2020 | 3/3/2020 | | PASS |
Michael Zawacki
|
|
|
Good vegetation and stabalization around main river channel. Pathway along ponds is pit run along sides, no regrowth.
|
General Inspection | 2/17/2020 | 2/17/2020 | 2/18/2020 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 1/31/2020 | 1/31/2020 | 1/31/2020 | | PEND |
Andy J. Long
|
|
|
no activity. open for revegetation checks.
Noted some BMPs left around VMP bridge that can be removed. Notified that some willow plantings will be placed along the bank of Veterans Pond.
|
General Inspection | 1/16/2020 | 1/16/2020 | 1/16/2020 | | DEFR |
Michael Zawacki
|
|
|
Will be at site next week for site prep of greenup. Currently frozen
|
General Inspection | 1/1/2020 | 1/1/2020 | 1/2/2020 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 12/17/2019 | 12/17/2019 | 12/17/2019 | | PASS |
Andy J. Long
|
|
|
No construciton activity, monitoring stabilization through Spring 2020. Disturbed areas have stabilized/revegeted. Rocky shore along NE side of Veterans Pond may need some additional seeding/planting. No temporary BMPs installed. Some construction material and signs are stockpiles near Stilson in VMP.
|
General Inspection | 11/29/2019 | 11/29/2019 | 12/2/2019 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 11/14/2019 | 11/14/2019 | 11/18/2019 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 10/30/2019 | 10/30/2019 | 11/1/2019 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 10/15/2019 | 10/15/2019 | 10/15/2019 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 9/27/2019 | 9/27/2019 | 10/1/2019 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 9/12/2019 | 9/12/2019 | 9/12/2019 | | CANC |
Michael Zawacki
|
|
|
|
General Inspection | 8/28/2019 | 8/28/2019 | 9/3/2019 | | PASS |
Michael Zawacki
|
|
|
SIte is in revegetation. Will continue to monitor.
|
Conference | 8/7/2019 | 8/13/2019 | 8/13/2019 | P | DONE |
Andy J. Long
|
|
|
Jute mesh along greenbelt path and Veterans Pond that was becoming loose has been removed as requested.
Permit is to remain open through October until some steps down to the wave structure are completed. Will need to continue to monitor revegetation.
|
General Inspection | 8/6/2019 | 8/6/2019 | 8/7/2019 | | PEND |
Andy J. Long
|
|
|
|
Site Final | 7/19/2019 | 7/22/2019 | 7/22/2019 | A | NR |
Andy J. Long
|
|
|
Tyler 208 724 3135
Project near completion: BLD permit for structures is also still open.
Construction and staging areas are now landscaped and stabilized. Work areas anc surrounding parking areas are freee of loose sediment or construction debris. Irrigation installed. Silt fence sediment barrier along Farmer's Union Canal has been removed.
New greenbelt pathways are complete and open to public. Slope between pathway and Veterans Pond has jute matting and has been hydroseeded. It is a rocky uneven surface, netting is not trenched and is installed horizontally. Minimal overlap, some areas already loose.
ESC requests for site final approval: - remove storm drain sediment bags installed on Stilson and on VMP between greenelt access and stilson. - remove flber rolls around bridges that are in the water. - provide specs/details on jute matting installation.
|
General Inspection | 7/5/2019 | 7/5/2019 | 7/9/2019 | | PASS |
Andy J. Long
|
|
|
Working on final phases of planting and hydroseeding. West construction installed.
Project contact Lance is now on other job, will schedule a site final with the onsite project foreman Tyler Ross.
No corrections requested. All temporary controls will need removal.
|
General Inspection | 6/20/2019 | 6/20/2019 | 6/24/2019 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 4/11/2019 | 4/11/2019 | 4/12/2019 | P | PASS |
Andy J. Long
|
|
|
Site walk through with RP. In channel work is near completion. Starting process to open up the berm at end of the new side channel around the habitat island.
No trackout from site, concrete washout is lined and being used for pathway paving operations. New slopes/banks have been hydroseeded.
Correction request to install sediment control buffer around excavated/disturbed areas next to the two bridges being installed around Veteran's Pond. Sweep up and clean area above the Farmer's Union Canal.
|
General Inspection | 3/11/2019 | 3/11/2019 | 3/12/2019 | P | PASS |
Michael Zawacki
|
|
|
Diversion dam removed, river is back up in cfs. Features have been completed. Crew is in river installing gates, area is blocked and pumps keeping dry. Some concrete work still needed by gate for canal. RPC will be back to do steps around gates when ready. Crew still working on new island area upstream of features. Both up and downstream are damed of and currently no flow in between. Crews are planting willows and working on stabalization. New path not started, covered under seperate permit.
|
General Inspection | 1/17/2019 | 1/18/2019 | 1/18/2019 | A | PART |
Michael Zawacki
|
|
|
Met with RP on site. No turbid discharges. Washout is torn and needs to be repaired. Some trackout, will be swept. Another load of rock may be brought in for entrance, some areas where trucks track wide and drive in mud.
|
General Inspection | 12/28/2018 | 12/28/2018 | 12/28/2018 | P | DONE |
Andy J. Long
|
|
|
see inspection from 12/27.
Notification of unearthed contaminated soils excavated in the new channel section of site, east of the habitat island.
IDEQ has been notified and working with site. Material will be removed and disposed per RCRA requirements.
|
General Inspection | 12/28/2018 | 12/28/2018 | 12/28/2018 | P | PASS |
Michael Zawacki
|
|
|
Working on river channel features. Workers parking in lot of Simplot Park. RPC doing features in channel, have rocks staged in western storage area. New well points installed in channel, no turbid discharge. Concrete and pump trucks on site, washout located on west end of project. No trackout from site. Excavator placing fill in pond for new path, turbidity curtain still working.
|
General Inspection | 11/16/2018 | 11/16/2018 | 11/16/2018 | P | PASS |
Andy J. Long
|
|
|
Inspection to check turbidity. Fill work occuring in Veteran's Pond to build new greenbelt pathway created some turbid water within the lake, as noted on Wednesday. (28 NTU wednesday 11/14, 44 NTU friday 11/16)
Upstream from project by Garden City pedestrian brings, sampled at 2.48 NTU
Sample at confluence of Farmer's Union (Boise River Diversion) at confluence of outflow of Vet's Pond was 4.2 NTU. Only a change of less than 2 NTU within the background, well under the 50 NTU limit.
To ensure turbidity in the lake did not cause a discharge, fill work was halted to allow settling and skimming of floating debris within the turbidity curtain zone.
Project is sampling turbidity daily and monitoring discharges. Approved.
|
General Inspection | 11/14/2018 | 11/14/2018 | 11/14/2018 | P | PASS |
Andy J. Long
|
|
|
WIP on compaction and preparation for foundations in dewatered river channel between cofferdams. River bottom material and concrete chunks have been removed. Water returning to the River from diversion pipe and well heads in channel is clear and was not churning up sediment at discharge point.
At upriver end of project the future channel to establish the habitat island is starting to be excavated. The material is then being hauled for fill into Veterans Pond along the canal side & future pathway route.
The area of fill at Veterans Pond has a turbidity curtain containment. A slight murkiness of the water leaving the pond and joining the diverted river water in Farmers Union was observed. Turbidity test at 12:45 today showed 28.4. Turbidity log was availalbe upon request. The result is above background levels but not above the 50 NTU limit. Samples taken in previous days were below 5.0 NTU. No visible plume was seen with the river water in Farmer's Union.
Other BMPs observed were secondary spill containment areas in staging yard and water truck working the haul routes to keep dust down.
|
General Inspection | 10/19/2018 | 10/23/2018 | 10/23/2018 | A | PASS |
Andy J. Long
|
|
|
9 AM fish salvage team
Team effort to salvage fish from the section river between cofferdams. Many fish and crawdads found including sculpin, white fish, brown trout, red band trount, suckers. Fish were counted by Water Quality crew. River bypass is operation, culvert to Farmer's Union is open. Mcmillen taking daily water quality samples. Pump dewatering river pool is going into Veteran's Pond and settling behind turbidity curtain.
|
General Inspection | 10/19/2018 | 10/22/2018 | 10/22/2018 | A | PASS |
Andy J. Long
|
|
|
check coffer dam installation
WIP on cofferdam frames. River is still flowing. No plumes or issues observed. Will be on site tomorrow AM
|
General Inspection | 10/16/2018 | 10/16/2018 | 10/16/2018 | P | PASS |
Michael Zawacki
|
|
|
Installing frame for dam and finishing diversion. Expecting to divert channell on 10/23 or 10/24.
|
General Inspection | 10/12/2018 | 10/12/2018 | 10/12/2018 | P | PASS |
Michael Zawacki
|
|
|
Multiple wellpoints for dewatering. No visible plume or differences between sides of turbidity curtain. Excavator doing prep work in river for diversion. Will follow up next week to check progress.
|
General Inspection | 9/25/2018 | 9/25/2018 | 9/25/2018 | P | PASS |
Michael Zawacki
|
|
|
Wellpoint in place, discharge is at 5.5 NTU.
|
General Inspection | 9/21/2018 | 9/21/2018 | 9/21/2018 | P | PASS |
Michael Zawacki
|
|
|
Wellpoint is in place. Dewatering is currently shut down until next week. No turbidity has made it past curtain. Allowing water to settle.
|
General Inspection | 9/20/2018 | 9/20/2018 | 9/20/2018 | P | PASS |
Michael Zawacki
|
|
|
Whitewater Park dewatering check up. Project superintendant Lance provided notification to ESC division
Did walkthrough of dewatering setup and took baseline for discharge area, 1.88 NTU. Contractor is still working on getting well point installed and dialed in.
|
Site Preparation | 9/14/2018 | 9/14/2018 | 9/14/2018 | A | PASS |
Andy J. Long
|
|
|
10 AM Walk through inspection with project superintendant Lance.
BMPs are installed and approved for construction:
- heavy duty construction entrances at Stilson Street and through ESP. - silt fence (SF) installations at brige crossings per SWPPP. - sediment control wattle installed to contain & treat runoff from staging area. RP to monitor and replace with SF if necessary- staging area has good pollution prevention measures in place including covered material storage, secondary containment areas, gravel parking and access to trailer, and spill kits. - water truck on site for dust control. - SWPPP/ESC plan on site for inspector review.
Tasks & recommended improvements for site:
- Post official SWPPP signage at designated main entrance to satisfy CGP 2017 requirements. Inlclude City of Boise ESC sign. - Provide covered dumpster. Investigate possibility of a recycling bin for cardboard boxes and other recyclables. Enery bags for large plastic wrappings? - report any significant changes or operations at site , including dewatering start ups to Boise ESC Inspectors Long & Zawacki.
|
Site Preparation | 9/14/2018 | 9/14/2018 | 9/14/2018 | A | PASS |
Michael Zawacki
|
|
|
Completed site walkthrough with project foreman.
|