Site Final | 3/6/2018 | 3/6/2018 | 3/6/2018 | P | PASS |
Andy J. Long
|
|
|
Construction complete, no disturbed area or loose materials remaining on site. Temporary BMPs (DI bags) that were installed for project have been removed. Permiter areas of building landscaped, sidewalk and gutters have been swept.
Former staging area across from project on 5th & Myrtle is under construction by ESI and covered seperately.
ESC permit conditions satisfied.
|
Site Final | 2/27/2018 | 3/1/2018 | 3/1/2018 | P | PEND |
Andy J. Long
|
|
|
needs clean up and stabilization of staging area. Okay for BLD final, ESC will be closed seperately
|
General Inspection | 2/26/2018 | 2/26/2018 | 2/27/2018 | | CANC |
Andy J. Long
|
|
|
rescheduled for site final
|
General Inspection | 2/9/2018 | 2/9/2018 | 2/15/2018 | | CANC |
Michael Zawacki
|
|
|
|
General Inspection | 1/25/2018 | 1/25/2018 | 1/25/2018 | | PASS |
Michael Zawacki
|
|
|
Majority of work complete. 5th street has been paved and silva cells are installed. Some plastic sheeting and scaffolding on building. Still is a storage yard in use, no dirt being tracked out or garbage blown from site. One lane of 5th and Myrtle still closed.
|
General Inspection | 1/10/2018 | 1/10/2018 | 1/12/2018 | | PASS |
Michael Zawacki
|
|
|
Working on silva cells and finishing sidewalk. No trackout coming from staging. Exterior work nearly complete. No dirt observed leaving site.
|
General Inspection | 12/26/2017 | 12/26/2017 | 12/26/2017 | | PASS |
Michael Zawacki
|
|
|
Majority of ground disturbance work. Interior and exterior work remain. Planters and silva cells look complete.
|
General Inspection | 12/11/2017 | 12/11/2017 | 12/11/2017 | | PASS |
Michael Zawacki
|
|
|
|
General Inspection | 11/24/2017 | 11/24/2017 | 11/24/2017 | | PASS |
Michael Zawacki
|
|
|
Installing sylva cells. All other work is interior. Site free of trash and trackout.
|
General Inspection | 11/9/2017 | 11/9/2017 | 11/9/2017 | | PASS |
Michael Zawacki
|
|
|
Alley has been paved, no large disturbed areas remain. Site is kept clean, no loose trash.
|
General Inspection | 10/25/2017 | 10/25/2017 | 10/26/2017 | | PASS |
Michael Zawacki
|
|
|
Only disturbed area is southern alley. Water will be piped into sylva cells onces complete. No dirt is leaving site. Trash was picked up and washouts were on site and maintained.
|
General Inspection | 10/10/2017 | 10/10/2017 | 10/10/2017 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 9/25/2017 | 9/25/2017 | 9/26/2017 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 9/8/2017 | 9/8/2017 | 9/8/2017 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 8/22/2017 | 8/24/2017 | 8/25/2017 | A | PASS |
Andy J. Long
|
|
|
|
General Inspection | 8/22/2017 | 8/22/2017 | 8/22/2017 | P | PEND |
Andy J. Long
|
|
|
Need to install inlet protection on Broad Street. Working with R-O-W contractor as well to remove inlets protection along stabilized portions of the LIV district roadway and stormwater improvements.
|
General Inspection | 8/11/2017 | 8/15/2017 | 8/22/2017 | P | CANC |
Andy J. Long
|
|
|
|
General Inspection | 8/7/2017 | 8/7/2017 | 8/11/2017 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 7/21/2017 | 7/21/2017 | 7/21/2017 | | PASS |
Andy J. Long
|
|
|
NO trackout, spills or fugitive dust observed. WIP on exterior finish and interior work. Seperate Broad Street LID project between 5th-6th street is also occuring. No corrections requested.
|
General Inspection | 7/6/2017 | 7/6/2017 | 7/6/2017 | | PASS |
Melissa Jannusch
|
|
|
WIP on road, curb, and gutters. Staging lane is clean, trash is contained. No ESC corrections observed.
|
General Inspection | 6/21/2017 | 6/21/2017 | 6/23/2017 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 6/6/2017 | 6/6/2017 | 6/8/2017 | | PASS |
Andy J. Long
|
|
|
WIP on exterior siding. All lanes around the block of Myrtle, 5th and Broad are closed and site work including new stormwater system is being installed. No trackout or fugitive dust observed. Concrete washout pans located on site. No corrections requested.
|
General Inspection | 5/22/2017 | 5/22/2017 | 5/22/2017 | | PASS |
Melissa Jannusch
|
|
|
|
General Inspection | 5/5/2017 | 5/5/2017 | 5/5/2017 | | PASS |
Melissa Jannusch
|
|
|
Okay. no trackout out of site.
|
General Inspection | 4/20/2017 | 4/20/2017 | 4/20/2017 | | CANC |
Melissa Jannusch
|
|
|
|
General Inspection | 4/5/2017 | 4/5/2017 | 4/5/2017 | | CANC |
Melissa Jannusch
|
|
|
|
General Inspection | 3/21/2017 | 3/21/2017 | 3/22/2017 | | PASS |
Melissa Jannusch
|
|
|
|
General Inspection | 3/6/2017 | 3/6/2017 | 3/6/2017 | | PASS |
Melissa Jannusch
|
|
|
|
General Inspection | 2/17/2017 | 2/17/2017 | 2/17/2017 | | PASS |
Melissa Jannusch
|
|
|
|
General Inspection | 2/2/2017 | 2/2/2017 | 2/8/2017 | | PASS |
Melissa Jannusch
|
|
|
No trackout. No corrections requested.
|
General Inspection | 1/3/2017 | 1/3/2017 | 1/10/2017 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 12/14/2016 | 12/14/2016 | 12/19/2016 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 12/19/2016 | 12/19/2016 | 12/19/2016 | A | PASS |
Andy J. Long
|
|
|
Vertical construction in progress. No trackout or muddy access areas observed. No discharges. Approved.
|
General Inspection | 11/29/2016 | 11/29/2016 | 11/29/2016 | | PASS |
Andy J. Long
|
|
|
Vertical construction in progress. Site perimeter has been swept, some minor dirt and gravel accumulation remain. No discharges or spills, trash and materials are contained. No corrections requested.
|
General Inspection | 11/14/2016 | 11/14/2016 | 11/17/2016 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 10/28/2016 | 10/28/2016 | 10/28/2016 | | PASS |
Andy J. Long
|
|
|
See also ESC15-1395 for Fowler project. Streets have been recently swept, with only minor accumulation of loose dirt. Vertical construction and wood framing in progress. No discharges spills, or trackout from work area.
|
General Inspection | 10/13/2016 | 10/13/2016 | 10/14/2016 | | PASS |
Andy J. Long
|
|
|
Receivng storm drains have sediment filter bags. Closed lanes and gutter areas have been cleaned recently, though some loose dirt & gravel remains.. Work occuring on the interior. No trackout or uncontained trash issues observed.
|
General Inspection | 9/28/2016 | 9/28/2016 | 9/29/2016 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 9/13/2016 | 9/13/2016 | 9/13/2016 | | PART |
Andy J. Long
|
|
|
Vertical construction in progress. No discharges or trackout to surrounding streets.
Correction request:
Increase sweeping frequency of the closed traffic lanes on 5th and Broad Street to prevent dirty runoff in case of precipitation..
|
General Inspection | 8/29/2016 | 8/29/2016 | 8/29/2016 | | CANC |
Evan Jenkins
|
|
|
|
General Inspection | 8/12/2016 | 8/12/2016 | 8/15/2016 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 7/28/2016 | 7/28/2016 | 7/29/2016 | | PASS |
Andy J. Long
|
|
|
DIs protected, no vehicle trackout. Need to continue to improve sweeping of closed lanes on Myrtle and 5th. No spills or discharges observed.
|
General Inspection | 7/13/2016 | 7/13/2016 | 7/13/2016 | | PASS |
Evan Jenkins
|
|
|
No issues observed. No discharges nor trackout leaving the site
|
General Inspection | 6/28/2016 | 6/28/2016 | 6/28/2016 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 6/3/2016 | 6/13/2016 | 6/14/2016 | P | PASS |
Andy J. Long
|
|
|
request sweep up on Broad and 5th within site perimeter.
Interior sweeping has occured as requested. Will need to continue to sweep regularly through out week.
|
General Inspection | 6/8/2016 | 6/8/2016 | 6/8/2016 | P | PART |
Andy J. Long
|
|
|
Request issued to sweep up the closed lanes around traffic to prevent fugitive dust and potential to combine with stormwater runoff.
Superindentant Bradden stated it will be cleaned this afternoon and tomorrow as needed. Will check back.
|
General Inspection | 6/2/2016 | 6/2/2016 | 6/3/2016 | | PART |
Andy J. Long
|
|
|
No trackout or discharges, BMPs installed.
Correction request - sweep up loose dirt and gravel bits within the fenced site perimeter that extends out into 5th and Broad. Looking a little dirty, housekeeping needed. Will check back early next week.
|
General Inspection | 5/18/2016 | 5/18/2016 | 5/18/2016 | | PASS |
Andy J. Long
|
|
|
WIP on concrete work for lower level parking garage. Site was swept and concrete washout better contained as last request. No discharges or runoff from site, no trackout or fugitive construction dust observed. Approved
|
Conference | 5/2/2016 | 5/3/2016 | 5/3/2016 | A | DONE |
Andy J. Long
|
|
|
Inspection notes from inspection conducted on Friday April 29:
Walk through BMP inspection with project management team member Bradden.
No significant trackout around site perimeter, leak proof designated concrete washout is provided in staging area. Stormwater DIs have inlet bags installed.
Correction requests: - sweep up corner of 5th & Broad (started while on site) - next week after concrete pouring activities and materials can be removed, street sweeping truck will be scheduled either Thursday or Friday.
Note- the stormdrain at 5th and Myrtle is not draining due system issue not related to construction.
Note: Site is seperating waste streams and designating materials suitable for recycling/re-use.
See also ESC15-01395
|
General Inspection | 4/26/2016 | 4/26/2016 | 4/26/2016 | | PASS |
Andy J. Long
|
|
|
Vertical construction in progress at the Fowler. No earthwork or offisite utility work occuring. Surrounding streets and gutters are free of loose dirt, trackout, or discharges. Staging area is clean and orderly. No corrections requested.
|
General Inspection | 4/11/2016 | 4/11/2016 | 4/11/2016 | | PASS |
Andy J. Long
|
|
|
WIP. No fugitive dust, no trackout from site or staging area, no spills or discharges observed including dewatering
|
General Inspection | 3/25/2016 | 3/25/2016 | 3/25/2016 | | PASS |
Andy J. Long
|
|
|
WIP on foundation. No trackout, no discharges. Permit sign onsite. Inlet on 5th street has sediment filter mat installed. No corrections issued at this time.
|
General Inspection | 3/10/2016 | 3/10/2016 | 3/10/2016 | | PASS |
Andy J. Long
|
|
|
WIP on foundation. BMPs installed include DI sediment filter mats, consrtuction entrance, and lined washout pit. No trackout or loose sediment on streets or in gutters around perimeter. No loose trash or spills observed. Approved.
|
General Inspection | 2/19/2016 | 2/19/2016 | 2/19/2016 | | PASS |
Daryl Spivey
|
|
|
|
General Inspection | 2/4/2016 | 2/4/2016 | 2/4/2016 | | PASS |
Andy J. Long
|
|
|
Work has now started. Site perimeter and staging area BMPs are installed. Permit sign posted. No trackout or discharges observed.
|
Site Preparation | 1/19/2016 | 1/20/2016 | 1/20/2016 | A | PASS |
Andy J. Long
|
|
|
3 PM on site conference & site preparation inspection.
Pre-construction meeting only. Construction and excavation to begin at start of February. Currently there is no discharge plan for dewatering at the moment but I informed them of dewatering permits with ACHD and additional requirements of a plan and water quality standards.
Discussed BMPs with project management team and stated that construction entrance, SWPPP signage, and inlet sediment protection must be installed.
Site to notify ESC division prior to site activation in February.
Approved. Site perimeter is clean and fenced in; yellow ESC sign posted.
|
Site Preparation | 1/19/2016 | 1/19/2016 | 1/19/2016 | P | CANC |
Andy J. Long
|
|
|
scheduled for 1/20
|
Site Preparation | 1/14/2016 | 1/15/2016 | 1/15/2016 | A | PEND |
Andy J. Long
|
|
|
Spoke with RP for project. Onsite ESC/SWPPP meeting will be scheduled for next week.
|
Site Preparation | 1/13/2016 | 1/13/2016 | 1/14/2016 | P | CANC |
Andy J. Long
|
|
|
rescheduled
|
General Inspection | 1/18/2017 | 1/18/2017 | | | |
Melissa Jannusch
|
|
|
|