General Inspection | 10/17/2018 | 10/17/2018 | 10/17/2018 | | CANC |
Michael Zawacki
|
|
|
|
DOC - Permit Finaled | 10/17/2018 | 10/17/2018 | 10/17/2018 | P | PASS |
Michael Zawacki
|
|
|
Witches hats all removed.
|
General Inspection | 10/2/2018 | 10/2/2018 | 10/2/2018 | | PASS |
Michael Zawacki
|
|
|
Still a witches hat on Tyra. Will final permit after it is removed.
|
General Inspection | 9/14/2018 | 9/17/2018 | 9/17/2018 | A | PASS |
Michael Zawacki
|
|
|
Parking addition completed. Area still needs to be landscaped. Silt fence still along canal.
|
General Inspection | 9/12/2018 | 9/12/2018 | 9/14/2018 | | CANC |
Andy J. Long
|
|
|
rescheduled
|
General Inspection | 8/24/2018 | 8/28/2018 | 8/27/2018 | A | PASS |
Michael Zawacki
|
|
|
All homes in neighborhood complete. Lots at entrance by cloverdalr are still exposed.
|
General Inspection | 8/23/2018 | 8/23/2018 | 8/24/2018 | | CANC |
Andy J. Long
|
|
|
rescheduled
|
General Inspection | 8/8/2018 | 8/8/2018 | 8/8/2018 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 7/24/2018 | 7/24/2018 | 7/24/2018 | | PASS |
Michael Zawacki
|
|
|
Last home under construction. All other lots completed and stable.
|
General Inspection | 7/9/2018 | 7/9/2018 | 7/9/2018 | | PASS |
Michael Zawacki
|
|
|
One home under construction. Large pile of fill in front yard. Some dirt on road from tree palnting at corner of Azure & Highwood.
|
Random Inspection | 6/22/2018 | 6/22/2018 | 6/22/2018 | P | PASS |
Michael Zawacki
|
|
|
Neighborhood is clean. Neighborhood DIs still installed. Few homes remain under construction,majority of neighborhood sold and landscaped.
|
General Inspection | 6/8/2018 | 6/8/2018 | 6/8/2018 | | PASS |
Michael Zawacki
|
|
|
Very few houses remain in development. Some dirt on streets from landscape crews. Site is overall in good condition.
|
General Inspection | 5/24/2018 | 5/24/2018 | 5/24/2018 | | PASS |
Andy J. Long
|
|
|
WIP on SFHs at west end of Azure Street. Subdivsion near full. Storm drains still have sediment bags installed.
Trash contained at sites. No corrections at this time.
|
General Inspection | 5/9/2018 | 5/9/2018 | 5/9/2018 | P | PASS |
Michael Zawacki
|
|
|
Most homes complete. Concrete washout has been cleaned and removed, roll pan brought on site for final foundations. Construction site cleanup company hired to clean and remove trash. Temps also being hired for cleanup help.
|
General Inspection | 4/30/2018 | 4/30/2018 | 4/30/2018 | P | PASS |
Andy J. Long
|
|
|
WIP on SFHs in Whitecloud by Hayden Homes. Storm drains have sediment protection, designated concrete washout pan on site, ESC permit signs posted on active homes. Trash contained at each site. Approved.
|
General Inspection | 4/19/2018 | 4/19/2018 | 4/20/2018 | | CANC |
Michael Zawacki
|
|
|
|
General Inspection | 4/4/2018 | 4/4/2018 | 4/4/2018 | | PASS |
Michael Zawacki
|
|
|
WIP on multiple SFH. Little dirt leaving sites, area is mostly clean. Some lots have lots of lumber scraps. Port O Pottie tipped over at Irving and Highwood, will also check other development to see who it belongs to.
|
General Inspection | 3/15/2018 | 3/20/2018 | 3/23/2018 | P | CANC |
Andy J. Long
|
|
|
|
General Inspection | 3/15/2018 | 3/15/2018 | 3/15/2018 | | CANC |
Andy J. Long
|
|
|
rescheduled
|
General Inspection | 2/28/2018 | 2/28/2018 | 2/28/2018 | P | FAIL |
Michael Zawacki
|
|
|
Site needs trash pickup. Some tras bins are overfull, other lots didn't have bin and have garbage laying all over lot. Was windy at time of inspection and trash was blowing down road. Lots of dirt on shoulder of road and sidewalks. Weather is supposed to be wet next few days and may cause an issue.
|
General Inspection | 2/15/2018 | 2/15/2018 | 2/16/2018 | | PART |
Michael Zawacki
|
|
|
Lots of trackout. Looks like street has been swept but lots of dirt remaining.
|
General Inspection | 1/31/2018 | 1/31/2018 | 1/31/2018 | P | PASS |
Michael Zawacki
|
|
|
Hayden Homes - White Clouds manager Phil Yates 208.608.3691 Streets are much cleaner. Crew is on site picking up trash and cleaning dirt of roads and sidewalks. Trash is being put into trash boxes.
|
Tracking Control | 1/18/2018 | 1/24/2018 | 1/25/2018 | A | FAIL |
Michael Zawacki
|
|
|
Talked to RP and gave him more time. Site wasn't cleaned.
|
Tracking Control | 1/16/2018 | 1/18/2018 | 1/18/2018 | A | PEND |
Michael Zawacki
|
|
|
Severe Trackout. Gave RP more time for cleanup. Rescheduled.
|
General Inspection | 1/11/2018 | 1/15/2018 | 1/16/2018 | A | FAIL |
Michael Zawacki
|
|
|
Excessive trackout onto Azure and sidewalks. Alleyway were homes are being built also covered in trackout. Old dry concrete needs to be removed from washout at corner of Azure & Highwood. Washout area needs gravel entrance, not just mud. Highwood also dirty but may be different builder, also going to talk to them. Contacted RP Thomas with Hayden Homes, 9:45 on 1-16, left message. Gave until Thursday since rain in forcast. Will issue SWO if area isn't taken care off.
|
General Inspection | 1/11/2018 | 1/11/2018 | 1/11/2018 | | CANC |
Andy J. Long
|
|
|
rescheduled
|
General Inspection | 12/27/2017 | 12/27/2017 | 12/28/2017 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 12/12/2017 | 12/12/2017 | 12/12/2017 | | PEND |
Michael Zawacki
|
|
|
Old washout still piled next to current washout. O Didn't see green permit signs at all active lots. Some trackout, inversion "snow" was covering most of site.
|
General Inspection | 11/24/2017 | 11/27/2017 | 11/27/2017 | A | FAIL |
Michael Zawacki
|
|
|
Washouts not cleaned up. Material on side of roads and sidewalks.
|
General Inspection | 11/17/2017 | 11/22/2017 | 11/24/2017 | A | PEND |
Andy J. Long
|
|
|
check for new wash out and some green signs posted.
|
BMP Violation | 11/13/2017 | 11/17/2017 | 11/17/2017 | P | PEND |
Andy J. Long
|
|
|
compliance deadline for washout extended to next Wednesday.
|
General Inspection | 11/9/2017 | 11/13/2017 | 11/13/2017 | P | FAIL |
Andy J. Long
|
|
|
Need to remove concrete washout and clean up area. Material should be disposed of properly at landfill, pit has some stormwater collected in it.
Correction request issued to Hayden Homes RP Tom
Stormdrains have sediment protection. Framing in progress on SFHs on Azure. Trash containment provided.
No trackout out of sub.
|
General Inspection | 11/9/2017 | 11/9/2017 | 11/9/2017 | | CANC |
Andy J. Long
|
|
|
|
Tracking Control | 10/23/2017 | 10/25/2017 | 10/30/2017 | A | PASS |
Michael Zawacki
|
|
|
Cleaned up trackout and fixed washouts. Said they are trying to get sweepers to show up.
|
General Inspection | 10/23/2017 | 10/23/2017 | 10/23/2017 | P | FAIL |
Michael Zawacki
|
|
|
Excessive trackout on both sidewal and streets. Multiple old washouts overflowing and washout around them. Syman documented both in their inspection but neither fixed. Walked around with project manager and he said he will get ti done today. Will schedule follow up to see if done.
|
General Inspection | 10/19/2017 | 10/19/2017 | 10/23/2017 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 10/4/2017 | 10/4/2017 | 10/4/2017 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 9/19/2017 | 9/19/2017 | 9/19/2017 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 9/4/2017 | 9/4/2017 | 9/5/2017 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 8/18/2017 | 8/18/2017 | 8/18/2017 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 8/3/2017 | 8/3/2017 | 8/3/2017 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 7/19/2017 | 7/19/2017 | 7/19/2017 | | PASS |
Andy J. Long
|
|
|
WIP on SFHs by Hayden Homes.
Granite Excavation no longer onsite, houses have seperate ESC permits. No discharges, spills or other issues. Trash containers provided, lined concrete washout is being utilized. No dust or significant trackout.
Approved.
|
General Inspection | 6/30/2017 | 6/30/2017 | 6/30/2017 | | PASS |
Andy J. Long
|
|
|
WIP on SFHs in Whitecloud by Hayden Homes. No significant trackout to streets. DI bags installed on storm drains. Lined concrete washout pit being used at west end of Azure. No corrections requested.
|
General Inspection | 6/15/2017 | 6/15/2017 | 6/16/2017 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 5/31/2017 | 5/31/2017 | 6/2/2017 | | PART |
Melissa Jannusch
|
|
|
Correction: Concrete washout needs maintenance.
No trackout Trash is contained DI bags ok. No other ESC issues
|
General Inspection | 5/12/2017 | 5/16/2017 | 5/17/2017 | P | CANC |
Andy J. Long
|
|
|
|
General Inspection | 5/12/2017 | 5/12/2017 | 5/12/2017 | | CANC |
Andy J. Long
|
|
|
rescheduled
|
General Inspection | 4/19/2017 | 4/26/2017 | 5/1/2017 | A | PASS |
Melissa Jannusch
|
|
|
Concrete washout has been maintenance. Correction: clean trackout in subdivision
|
General Inspection | 4/18/2017 | 4/18/2017 | 4/19/2017 | | PASS |
Melissa Jannusch
|
|
|
Left message with RP Thomas from Hayden homes. Other RP Jerry is longer responsible for the project. Request maintenance of concrete washout sweeping of trackout on Highwood and Irving and replacement of the DI bag near trackout area. The rest of the subdivision is ok.
|
General Inspection | 3/31/2017 | 3/31/2017 | 3/31/2017 | A | PASS |
Andy J. Long
|
|
|
Hayden Homes working on SFHs. Concrete washout pit provided on NW corner of Azure.. Storm drain inlets have filter bag protection. No trackout or trash violations. Will need to install inlet protection when work begins on Azure.
|
Random Inspection | 2/24/2017 | 2/24/2017 | 2/24/2017 | P | PASS |
Andy J. Long
|
|
|
Site grading, infrastructue, and utility installation complete. Landscping between medians in progress. New DIs have sediment protection installed. No corrections rquested.
|
General Inspection | 11/29/2016 | 11/29/2016 | 11/29/2016 | P | PART |
Andy J. Long
|
|
|
Subdivision roads and utilities now complete and parcels preped for SFHs by Hayden HOmes. Permit and SWPPP info posted. No significant trackout, uncontained trash or spills observed. No activity at time of inspection
Corrections: - install DI bags on all new storm drains. Will notifiy Hayden Homes for SFH requirements - needed new concrete washout.
|
Conference | 9/23/2016 | 9/26/2016 | 9/28/2016 | A | PEND |
Andy J. Long
|
|
|
no activity. Permit sing now posted. Need to install construction entrance by sign or provide paving schedule. No trackout. A rock entrance is installed at the NE corner of work area.
|
General Inspection | 9/23/2016 | 9/26/2016 | 9/26/2016 | A | CANC |
Andy J. Long
|
|
|
|
Site Preparation | 9/23/2016 | 9/23/2016 | 9/23/2016 | P | CANC |
Andy J. Long
|
|
|
data entry error
|
BMP Violation | 9/21/2016 | 9/23/2016 | 9/23/2016 | A | PART |
Andy J. Long
|
|
|
Check on track out, construction eneterances--
No activity. No construction entrance installed. Permit sign and SWPPP now installed. No wind blown dust or equipment operating dust.
|
BMP Violation | 9/20/2016 | 9/21/2016 | 9/21/2016 | P | PART |
Mike Jordan
|
|
|
check for dust control. Water truck on site, noted dust control in progress when on site this morning.
Did note track out onto irving and Cloverdale. A verbal correction was given to Hayden Homes to Sweep all track out and provide controlled construction enterance and exits with top dressing. Also noted no SWPPP or ESC permit sign posted. A reinspection has been scheduled for Friday Sept. 23rd.
|
BMP Violation | 9/20/2016 | 9/20/2016 | 9/20/2016 | P | PART |
Andy J. Long
|
|
|
No water truck on site and excessive dust plumes leaving site boundaries.
Verbal correction request to onsite foreman Jake with Granite Construction to halt work until water truck is onsite.
Work stopped, I provided new permit sign and waited for 15 minutes until water truck arrived.
Jake stated water truck will be onsite at least once per every 2 hours to hit the haul road between stockpile of drain rock and seepage trench.
|
BMP Violation | 8/25/2016 | 8/30/2016 | 8/30/2016 | A | PEND |
Andy J. Long
|
|
|
check for location permit and SWPPP on site. Unable to locate at this time
|
General Inspection | 8/24/2016 | 8/25/2016 | 8/25/2016 | A | PART |
Andy J. Long
|
|
|
No activity at site. No windblown dust issues observed. No trackout or spills. DI's have sediment bags.
Need to post permit sign and SWPPP info. Corrections in progress.
|
General Inspection | 8/23/2016 | 8/24/2016 | 8/24/2016 | P | CANC |
Andy J. Long
|
|
|
Check to see if fugitive dust issues. Warning issued 8/22
rescheduled for tomorrow AM
|
BMP Violation | 8/23/2016 | 8/23/2016 | 8/23/2016 | P | PART |
Andy J. Long
|
|
|
WIP on grading and earth moving. Observed dust plumes crossing project boundaries and no dust control water truck operating.
Discovered water truck was on site waiting for a flat tire repair, buit was operating previously.
Issued warning to RP Jerry to control dust and get the truck fixed ASAP. Remindinged him of ESC permit conditions. Will check site tomorrow for water truck in action.
|