Permit Information
Permit NumberESC17-00774
StatusFinaled
Name JIM CONGER
Site Address 2980 S MILLBROOK WAY
Project NameHarris Ranch CID No1 Relocatio
Customer Number 
ePlanReviewNo
Description
The relocation of Warm Springs Creek through the limits of the Dallas Harris Estates Development to extend from the Idaho Power corridor through Harris Ranch and connecting into the new box culvert crossing at Warm Springs Avenue.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
General Inspection1/9/20201/9/20201/9/2020 CANC
DetailsMichael Zawacki
DOC - Permit Finaled1/9/20201/9/20201/9/2020PPASS
DetailsMichael Zawacki
General Inspection12/25/201912/25/201912/26/2019 CANC
DetailsAndy J. Long
General Inspection12/10/201912/10/201912/10/2019 PASS
DetailsMichael Zawacki
General Inspection11/25/201911/25/201911/25/2019 PASS
DetailsMichael Zawacki
Messaged Lazoro with Black Rock about some wind blown trash on north side of parkcenter.
General Inspection11/8/201911/8/201911/12/2019 PASS
DetailsAndy J. Long
No corrections at this time. Permit open to check spring flows
General Inspection10/24/201910/24/201910/25/2019 PASS
DetailsMichael Zawacki
Barber Valley HOA is taking care of watering and trash cleanup.
General Inspection10/9/201910/9/201910/9/2019 CANC
DetailsAndy J. Long
General Inspection9/24/20199/24/20199/24/2019 CANC
DetailsAndy J. Long
General Inspection9/9/20199/9/20199/9/2019 PASS
DetailsMichael Zawacki
Creek is dry, banks vegetated. Looks like someone has started to clean the trash.
General Inspection8/23/20198/23/20198/23/2019 CANC
DetailsAndy J. Long
General Inspection8/8/20198/8/20198/8/2019 PASS
DetailsMichael Zawacki
Creek is now dry and vegetation dormant. Fence has been put up to prevent trash from blowing into creek on next phases of townhomes. Looks like someone has started to clean the trash around area.
General Inspection7/24/20197/24/20197/24/2019 PASS
DetailsAndy J. Long
General Inspection7/9/20197/9/20197/9/2019 PASS
DetailsMichael Zawacki
Creek not flowing, irragation in place.
General Inspection6/24/20196/24/20196/24/2019 CANC
DetailsAndy J. Long
General Inspection6/7/20196/7/20196/11/2019 PASS
DetailsMichael Zawacki
Creek no longer flowing. Still needs a trash cleanup. Blackrock homes has backfill very close to creek on south side of parkcenter.
General Inspection5/23/20195/23/20195/23/2019 PART
DetailsMichael Zawacki
Creek needs trash picked up and debris blocking flow .
General Inspection5/8/20195/8/20195/8/2019 PASS
DetailsMichael Zawacki
Irragation system now works. Creek needs trash picked up.
General Inspection4/23/20194/23/20194/23/2019 PART
DetailsMichael Zawacki
Irrigation system has been repaired and growth is on banks.
Lots of trash in creek channel, first feature above park center hasn't worked, area is getting undercut and lots of erosion.
General Inspection4/8/20194/8/20194/8/2019 PASS
DetailsMichael Zawacki
One section upstream of Parkcenter may be compromised, parties notified. Grass and vegetation growing in well, needs trash pickup. Area next to creek is now under construction.
General Inspection3/22/20193/22/20193/22/2019 CANC
DetailsAndy J. Long
General Inspection3/7/20193/7/20193/7/2019PPEND
DetailsAndy J. Long
final gabion check dam north of parkcenter appears to be too high and water is not staying along the flow line and eroding the channel banks.

Will consult with engineer Dave Powell and Boise PW engineering.
General Inspection2/25/20192/25/20192/26/2019 PASS
DetailsMichael Zawacki
Creek flowing as designed, no bank issues.
General Inspection2/8/20192/8/20192/8/2019 PASS
DetailsMichael Zawacki
Creek is stable. HOA or other group needs to take responsibility and do a trash cleanup walk.
General Inspection1/24/20191/24/20191/24/2019 PASS
DetailsMichael Zawacki
Creek will need trash pickup.
General Inspection1/9/20191/9/20191/9/2019 PASS
DetailsMichael Zawacki
Creek banks are stable.
General Inspection12/25/201812/25/201812/26/2018 PART
DetailsMichael Zawacki
Creek is stable. Will need trash pick up.
General Inspection12/10/201812/10/201812/10/2018 CANC
DetailsAndy J. Long
General Inspection11/23/201811/23/201811/27/2018 PASS
DetailsAndy J. Long
Project complete and is in revegetation phase. No corrections requested
General Inspection11/8/201811/8/201811/9/2018 PASS
DetailsMichael Zawacki
Work complete and stable.
Channel is collecting trash.
General Inspection10/24/201810/24/201810/24/2018 PASS
DetailsMichael Zawacki
Creek work is complete and sides stable. HOA or other group need to keep clean and pick up all the trash that has blown in from home construction.
General Inspection10/9/201810/9/201810/9/2018 PEND
DetailsAndy J. Long
Need trash picked up in section north of Parkcenter.
General Inspection9/21/20189/21/20189/21/2018 PASS
DetailsMichael Zawacki
Relocation is completed, vegetation has grown in. Some wind blown trash in channel, need to see who is responsible for up keep. Permit will remain open.
General Inspection9/5/20189/6/20189/10/2018APASS
DetailsAndy J. Long
NO new activity or recent construction. No water in Warm Springs creek except close to the River. Willows on lower section are growing well, upper section was too dry so many of the cuttings have dried out and died. No erosion, loose netting or other issues observed.
General Inspection8/30/20188/30/20189/5/2018 CANC
DetailsAndy J. Long
General Inspection8/15/20188/15/20188/15/2018 PASS
DetailsMichael Zawacki
Creek has no flowing water coming in. Irragation is in place for vegetation, coming in nicely.
General Inspection7/31/20187/31/20188/1/2018 PASS
DetailsMichael Zawacki
No new activity on creek. Banks are irrigated and growing well. Willows aresprouting, no ESC issues and will continue to monitor.
General Inspection7/16/20187/16/20187/16/2018 PASS
DetailsAndy J. Long
No new activity or changes on the Warm Spring Creek relocation. Site has irrigation installed and operating for the willows and bankside grasses. No corrections requested at this time.
General Inspection6/29/20186/29/20186/29/2018 PASS
DetailsMichael Zawacki
Creek is clear and willows growing. Some disturbed area where new channel was connected to go under park center. SOme windblown trash has blown into creek. No issues where Knife River connected new channel. Rocks have been placed in rill that formed upstream of new box culvert.
General Inspection6/14/20186/14/20186/14/2018PPASS
DetailsMichael Zawacki
Creek has been opened, old channel being filled.
Steps where taken to keep out sediment before allowing water to flow through.
General Inspection6/5/20186/8/20186/8/2018PPEND
DetailsAndy J. Long
NO flow through creek. No activity. No repair to large gully @ Harris Ranch Road and Parkcenter as requested. Sediment from gully is trapped behind barrier blocks and will need removed.
General Inspection6/5/20186/5/20186/5/2018 PEND
DetailsAndy J. Long
Creek channel is now open. Rip rap channel at Warm Springs by-pass was rinsed prior to allowing flow to river. Rinse water was dewater to adjacent vegetation.

No repair on gully at Parkcenter and Harris Ranch Road.
General Inspection5/15/20185/21/20185/21/2018APASS
DetailsMichael Zawacki
follow up
Knife river is going to fix rill forming. No issues on site, BMPs still in place.
General Inspection5/15/20185/15/20185/15/2018PFAIL
DetailsAndy J. Long
Need to repair and correct eroded bank at corner of Parkcenter and Harris Ranch Road. Roadway runoff is moving to fast and cutting into the bank of the creek and depositing sediment behind check dam structure in channel.

Emailed photos to engineer Dave @ Riverridge. He will have crews repair with a slope drain or lined channel to prevent further runoff.
General Inspection5/4/20185/4/20185/8/2018PPEND
DetailsAndy J. Long
Supplemental irrigation to be turned on next week. Banks are vegetating pretty well. Area is still being monitored for stabilization. Roadway runoff from Barber Drive has caused erosion just north of the new culvert...This area will soon be under construction again and addresses issued as part of master plan (per Dave Powell w/ RiverRidge)
General Inspection4/6/20184/9/20184/11/2018APEND
DetailsAndy J. Long
No corrections issued. Vegetation for banks is establishing well on coir mat, but not the straw netted mat. Some minor rilling will need to be addressed.

Working on request to Harris Ranch facilities crew to pick up trash in original channel of Warm Springs Creek.
General Inspection3/29/20183/29/20184/6/2018PPEND
DetailsAndy J. Long
No turbidity issues observed. Grass from hydroseed is growing. Walk through scheduled for Modany 4/9
General Inspection11/20/201711/20/201711/20/2017APASS
DetailsMichael Zawacki
Creek has been hydroseeded. Willow cuttings have been planted. Irragayion system installed.
General Inspection11/2/201711/2/201711/3/2017PPEND
DetailsAndy J. Long
WIP on pathway. Route through pasture is fine, but Warm Springs creek has been disturbed for placement of new culverts under new path. Will need immediate implementation of stabilization measures.
General Inspection10/24/201710/24/201710/24/2017APASS
DetailsMichael Zawacki
WIP. No geojute yet installed.
General Inspection10/13/201710/13/201710/13/2017APEND
DetailsMichael Zawacki
Crews still onsite. WIP.
Compare install to spec sheets provided.
General Inspection9/28/201710/10/201710/12/2017APEND
DetailsAndy J. Long
WIP on installing TRM and ECBs on channel. No violations observed in staging areas. Water leaving creeek area is clear. Will check back on installation specs for TRM/ECBSs
General Inspection10/3/201710/4/201710/4/2017PPEND
DetailsAndy J. Long
New channel for Warm Springs Creek is now complete and is in the process of being prepped for installation of turf reinforcement matting (TRM) installation along the bottom of the channel as well as seeding and placement of coconut and jute matting along the upper sections of the banks. The TRM will be covered in rip rap in some areas.

Work is supposed to resume next week. No trackout from site staging areas, no correction requests issued.
General Inspection9/28/20179/28/20179/28/2017PPEND
DetailsAndy J. Long
New channel has been dug. No bank vegetation or other revegetation implemented yet. Install channel reinforcement blanket. Does not appear to be staked down in many areas.

Call in to designer/installer to come check work.
General Inspection8/18/20178/22/20178/24/2017PPASS
DetailsAndy J. Long
No issues or discharges from dewatering locations. No fugitive dust observed.

Correction request:

Pick up trash piles of excavated pipe and other material.

General Inspection8/4/20178/14/20178/18/2017PCANC
DetailsAndy J. Long
General Inspection8/3/20178/4/20178/4/2017APEND
DetailsAndy J. Long
report of dewatering, no dewatering plan or notice received

Dewatering operation set up for land application to pasture land between Parkcenter Blvd and Warm Springs Bypass road. North of parkcenter and to the west of Barber Drive water is being detained for infiltration/evaporation.

No discharges offsite or to waterway/storm drain.. Slow pump rate, water coming up is not turbid.

Will follow up for update to SWPPP.
Site Preparation7/19/20177/20/20177/20/2017APASS
DetailsMelissa Jannusch
Okay to start. wattle installed. SWPPP up to date.

Jason Phone #: ###-####
Conference7/17/20177/17/20177/17/2017APASS
DetailsMelissa Jannusch
Pre-construction meeting:

Call in site preparation inspection before work begins and after BMPs are installed ###-####

Sign will be located on old hickory by the job site trailer. The SWPPP plan is located on Old Hickory as well. Site meetings are held on Wednesdays at 9:00AM in the job trailer.

Ensure use of dust control during the stripping and excavation phase which will begin next week. Comply with all other ESC requirements for City of Boise and EPA as well.

Dewatering:
Dewatering will take place. The excavator plans to strip the land first, dig test pits to determine the GW level, and then begin dewatering. The plan is to let the water sheet flow into the field across warm springs. This section of road will be closed during this time.

Call in an inspection to City of Boise before dewatering beings and after the dewatering set up is in place. This is to ensure the set up matches the approved plan and to reduce the chance of stopping the dewatering once it is underway if a change does need to be made.

Revegetation/stabilization:
Will be occurring during August and September. Supplemental irrigation will be installed and used to establish the vegetation. The channel will be lined with rip rap for stabilization.