Information based on query as of Friday, May 10, 2024.
Permit Information
Permit NumberESC18-00983
StatusIssued
Name STEVE SEARS
Site Address 5075 S HOLCOMB RD
Project NameMoxie Ridge Subdivsion
Customer Number 
ePlanReviewNo
Description
Application to rough grade the entire subdivision site.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
General Inspection8/7/20208/7/20208/11/2020 PASS
DetailsMichael Zawacki
WIp on homes on Mendota, all slabs have been poured.
WIP on footings and slabs on south side of Donzee, large lined washout on north side, no dumped washout on any sites.
WIP on framing on tiger lilly.
Crerw is starting work on western end of neighborhood. Water and sewer pipes staged. Did not see a water truck.
General Inspection7/23/20207/23/20207/23/2020 CANC
DetailsAndy J. Long
General Inspection7/8/20207/8/20207/8/2020 PASS
DetailsMichael Zawacki
WIP on multiple homes on Mendota, no issues, streets and sidewalks clean, no loose trash.
Some foundation work on Danzee, no new pours, backfill all on lots.
WIP on multiple homes on Tiger Lilly. No new pfoundation work.
General Inspection6/23/20206/23/20206/23/2020 PASS
DetailsMichael Zawacki
Lots of activity on Mendota, some trusses stored on road, work areas clean and no tracking.
1 foundation begun on Danzee.
Tiger Lilly clean. Washout never repaired with entrance, no tracking.
General Inspection6/8/20206/8/20206/12/2020 PASS
DetailsAndy J. Long
WIP on homes by Black Rock. No issues, lined concrete washout pit on TIger Lily
General Inspection5/22/20205/22/20205/22/2020PPASS
DetailsAndy J. Long
No hillside erosion issues observed after large rain event. HOmes permitted separately by Black Rock
General Inspection5/18/20205/18/20205/19/2020 PASS
DetailsMichael Zawacki
All foundation on Mendota poured, few homes framed, workers on interior.
Workers are all parked on Mendota, no trash or tracking.
Hillsides above and below Rutbie have good vegetative cover.
No activity on Danzee.
All foundations on south of Tiger Lilly completed, preppin to pour pads on north side. Washout still in garage.
No issues.
General Inspection5/1/20205/1/20205/1/2020PPASS
DetailsAndy J. Long
Minimal activity. No violations, erosion issues observed. BMPs installed, revegetation working well to prevent erosion
General Inspection4/29/20204/29/20204/29/2020PPASS
DetailsMichael Zawacki
5 homes framed on bottom section. Workers on site are doing mechanical. All foundations on lower section poured. Strrets and sidewalks are clean.
Hillside is well vegetated, still has same 1 rill running down, it has been filled and retackified, no new growth.
No work along Danzee, lots are bare, weeds starting to grow.
Foundations on north of Tiger Lilly poured, working on foundations on south side.
No crews at site doing foundation work today, washout in use, located in garage of new pad.
General Inspection4/15/20204/15/20204/17/2020 PASS
DetailsMichael Zawacki
WIP on framing on lower section, looks like all slabs completed.
Upper section has concrete crew on site doing foundation work. Pump truck is on site, washout is in one of the garages.
No esc issues.
General Inspection3/31/20203/31/20203/31/2020 PASS
DetailsMichael Zawacki
One home being framed on bottom section.
One excavator working on tiger lilly starting to excavated for foundation.
Roads and sidewalks clean, power broom on site.
General Inspection3/16/20203/16/20203/16/2020PPART
DetailsMichael Zawacki
No workers on site. All foundations on lower section have been poured, strrets and sidewalks clean.
Up on tiger lilly there is lots of dirt on sidewalks and washout is about full. Sent message to listed RP clint.
General Inspection3/6/20203/6/20203/6/2020 PASS
DetailsAndy J. Long
WIP on foundations on Tiger Lily. Using lined concrete washout in one of the driveways on north side of street.

Blackrock is in charge of SFH construction.

Will work with developer to get correct installation of check dams.

No discharges, trackout or other violations.
General Inspection2/20/20202/20/20202/20/2020 PASS
DetailsMichael Zawacki
WIP on 2 foundations, no vertical construcrtion has begun. Crews hauling backfill from top, hear it is going to Harris Ranch.
Rilling on hillside looks like it has been repaired at top and fresh tackifier placed.
Site is frozen, no tracking at time of inspection.
General Inspection1/28/20202/5/20202/10/2020AFAIL
DetailsMichael Zawacki
3 lower check dams haven't been repaired. Above is still full of sediment, some have flow lines around, middle isn't lower. Sediment is currently frozen.
Looks like is new berm up top, doesn't look like it has been overtopped anywhere.
General Inspection1/27/20201/28/20201/28/2020PPART
DetailsAndy J. Long
No offsite discharges, BMPs installed

Corrections needed:
- clean up and maintain check dams at bottom of slope and between road. Requested that installation be inspected to make sure the center has a v-notch to prevent water from flowing around check dam.

- install new slope diversion berm at top of slope to reduce size of puddle holding area just above the large rill on the slope.

Notified Steve, he said corrections have been ordered. Follow up scheduled for next week.
General Inspection1/14/20201/14/20201/14/2020 PASS
DetailsMichael Zawacki
snow covered
General Inspection12/27/201912/27/201912/30/2019 PART
DetailsMichael Zawacki
Sent message to RP. Crews hauling out stockpile from top, some tracking within site.
Home construction is keeping street and sidewalks swept, no obstructions.
General Inspection12/12/201912/12/201912/13/2019PPASS
DetailsAndy J. Long
No subdivision erosion or runoff issues after rail fall. Slope diversion berm is intact.

Working with Blackrock on temporary backfill placement so that sidewalks are not blocked and material is not stored in the gutter.
General Inspection12/4/201912/4/201912/4/2019 PART
DetailsMichael Zawacki
Concrete and foundation work on lower section, no activity on upper area.
Washout in use.
Some tracking and dirt on road from crews, needs to be cleaned end of day.
General Inspection11/19/201911/19/201911/19/2019 PASS
DetailsMichael Zawacki
Work on lower section. Area is clean. No work has started on upper section.
General Inspection11/4/201911/4/201911/4/2019 PART
DetailsMichael Zawacki
Multiple foundations poured on Mendota. Washout on site, lined and has stabalized road leading to it. Sidewalks look like they were scraped with blade, still need to be broomed off.
No workers at site.
Hillside has good vegetation, couple of spots of rilling from concentrated flow. Still some stockpiles on upper section, have growth on them and are stable.
No home construction has begun on upper section, no issues.
General Inspection10/18/201910/18/201910/18/2019 PASS
DetailsMichael Zawacki
Work has started on foundations in lower section. Lined washout is within garage of one of the homes, gravel entrance leading to it. Landscapers with sod on site. Area is clean.
General Inspection10/3/201910/3/201910/4/2019 CANC
DetailsAndy J. Long
General Inspection9/17/20199/17/20199/17/2019PFAIL
DetailsAndy J. Long
post rainfall inspection

No sediment runoff from disturbed areas observed. Site stormwater system is built, slope is very well vegetatated, no new erosion observed.

Fence installation crew had cement truck washout onto ground next stockpile. Final concrete washout warning at this site. Must be cleaned up before end of week.

Corrections needed:
- check that all storm drains have properly installed sediment protection
- fix berm and drainage swale at top of slope corner to direct upland water away from the existing rills from last season.

Notified RP Steve.
General Inspection9/11/20199/11/20199/11/2019 PASS
DetailsMichael Zawacki
Fence crew on site installing vinyl fencing. Front end loader at site cleaning up junk such as brush. Excavator and dump truck in lower section. Some dirt on site roads.
General Inspection8/27/20198/27/20198/29/2019 PASS
DetailsAndy J. Long
Some minor activity. Sprinklers on the revegeted hillside.
General Inspection8/12/20198/12/20198/12/2019PPART
DetailsAndy J. Long
No discharges, trackout, or fugitive dust. Revegetated slopes have irrigation installed. Roads and gutters are installed.

Corrections need at NW corner of upper level:

- fix break in berm above the start of a large
- install check dam in drainage channel, direct channels outflow away from the slope
General Inspection7/31/20197/31/20197/31/2019 PASS
DetailsMichael Zawacki
Lots of stockpiles of rock brought in, looks like seepage bed rocks.
No activity on any home sites. No trackout or dust at time of inspection.
General Inspection7/16/20197/16/20197/17/2019 PASS
DetailsMichael Zawacki
No new construction activities. Lots of dirt on road inside project, none leaving site.
General Inspection6/27/20197/1/20197/2/2019APASS
DetailsMichael Zawacki
Streets are paved, curb and sidewalk done. Hillsides have good cover, stockpiles have growth. Currently hauling some backfill. Dust from one truck turning around.
General Inspection6/26/20196/26/20196/27/2019 CANC
DetailsAndy J. Long
General Inspection6/11/20196/11/20196/11/2019PPASS
DetailsMichael Zawacki
Sidewalks have been installed, road bed prepped. No dust or ESC issues.
General Inspection5/30/20195/30/20195/30/2019PPASS
DetailsMichael Zawacki
Work on sidewalks and curbing. Water truck spraying road bed. Roll pan washout on site. No trackout or ESC issues.
General Inspection5/21/20195/21/20195/21/2019 PASS
DetailsMichael Zawacki
All water staying on site. No workers at site. Hillside vegetation growing in. Some rilling on road bed going down hill, all dirt stays on site.
Tracking Control4/30/20195/2/20195/2/2019APASS
DetailsMichael Zawacki
Entrances have been closed, area is prepped for paving. Road has been cleaned.
General Inspection4/30/20194/30/20194/30/2019PPART
DetailsMichael Zawacki
Some trackout onto Holcomb, lots of dust when cars run it over. Entrance is compacted and corner cut.
Lots of dust when trucks pull into entrance.
RP notified and follow up scheduled.
General Inspection3/29/20193/29/20194/1/2019PCANC
DetailsAndy J. Long
General Inspection4/1/20194/1/20194/1/2019PFAIL
DetailsAndy J. Long
Corrections needed:
- sweep shoulder and entrance at Holcomb
- repair barrow ditch erosion occuring at top portion of site (west boundary) that directs water down the corner of the cut slope.
- maintain any loose or displaced wattles
- remove or stabilize large stockpiles.
- make sure that berm at top of slope is intact and level across the entirere length
- smooth out tire ruts that channels and concentrates sheet flow
- fix erosion at the northeast corner of site above the bend in Holcomb Road.

RP steve states that erosion repairs and wattle maintenance are to occur this week. Will schedule a follow up site walk. Verbal correction requests to Steve.
General Inspection2/7/20192/7/20192/7/2019PPASS
DetailsMichael Zawacki
Talked to RP.
Will close upper access from tiger lilly when pipe work completed. Street has been cleaned. No one on lower area of site.
General Inspection1/31/20191/31/20191/31/2019PFAIL
DetailsMichael Zawacki
Lots of trackout onto Tiger Lilly, poor ntrance, all workers parking on street. Holcomb has been patched after work by Track Utilities, no trackout from below.
General Inspection1/24/20191/24/20191/24/2019PFAIL
DetailsMichael Zawacki
Track utilities working on Holcomb. Lots of dirt on shoulder. Site is frozen at time of inspection, starting to thaw. Rilling starting on longer slopes.
Trackout onto tiger lilly, one person parked in mud.
Sent message to RP.
General Inspection1/2/20191/3/20191/7/2019APASS
DetailsAndy J. Long
Tracking Control12/17/201812/17/201812/17/2018PFAIL
DetailsMichael Zawacki
Working on installation on top of project. Entrance has been constructed onto Holcomb, is some trackout.
Tracking Control12/7/201812/11/201812/11/2018PFAIL
DetailsMichael Zawacki
No entrances installed.
General Inspection12/7/201812/7/201812/7/2018PFAIL
DetailsMichael Zawacki
Working on sewer/utilities. Nonworking construction entrance, tracking onto Holcomb.
General Inspection11/15/201811/15/201811/15/2018PPASS
DetailsMichael Zawacki
Work on sewer has begun, HI Grade underground doing work at entrance. Someone has offroaded all over hillsides and across BMPs.
General Inspection11/1/201811/1/201811/1/2018PPASS
DetailsAndy J. Long
Hillside erosion control installation are now complete. Horizontal tracking, slope interupting wattles, and hydroseed application conducted in ideal time frame.

No trackout, will need to install better construction entrance at Holcomb if dump trucks are pulling from the large stockpile.
General Inspection10/19/201810/19/201810/19/2018PPASS
DetailsMichael Zawacki
Wattle has been installed on hillside and on flat along site road. Access from Tiger Lilly has been closed of. Road has no check dams and will need to be monitored.
General Inspection10/3/201810/9/201810/9/2018APEND
DetailsAndy J. Long
check on wattle installation...

Wattles staged. No offsite runoff. Lots of run on coming into site at lower entrance. Will need to figure out way to convey water beyond this entrance to avoid muddy entrance & trackout.
General Inspection9/28/201810/1/201810/3/2018APASS
DetailsAndy J. Long
Majority of mass grading is complete. Berms and ditches to be installed on top of ridge to divert water away from slopes. Slopes have had topsoil spread and horizontally tracked.

Next week installation of wattles is to begin. Wattles to be installed every 25 vertical feet on slopes. Will use heavy duty bark wattles. Wattles MUST be trenched in 2-3 inches, staked every4-5 ft, and have overlapping ends. Inspection scheduled to check on installation next week. After wattles are installed, hydroseeding will be completed on all disturbed areas to be inactive for stabilization. Should be near the end of October. Pipe work will begin in November for sewer & water. Request to beef up construction entrance at that time to prevent trackout. Large stockpiles at top and bottom of site must be tacified once fully inactive. RP to review stabilization requirements of 2.2 in CGP 2017.

No trackout, wind blown dust, loose trash, or discharges observed. Follow up scheduled.
General Inspection9/28/20189/28/20189/28/2018PCANC
DetailsAndy J. Long
rescheduled for site meeting with RP Steve. Mass grading is complete.
General Inspection9/21/20189/21/20189/21/2018PPASS
DetailsMichael Zawacki
No dust or trackout. No hillside bmps or tracking. Will need to meet with RP after L3 is finished to see what the plan is for stabalization.
General Inspection9/13/20189/13/20189/13/2018APASS
DetailsMichael Zawacki
Rough grading expected to be completed in two weeks, and will be handed to owner for utilitie contractors. Two large stock piles to remain on site. No dust or trackout observed. Will need to work with owner to get BMPs installed.
General Inspection9/5/20189/5/20189/5/2018PPART
DetailsMichael Zawacki
Entrance onto tiger lilly is blocked off. Water tank on site. Grading is currently on flat below hill. No stabalization or hillside BMPs installed.
Lots of dust on grubbing, talked with operator, water wagon was on way down hill. Will need to continue to monitor for dust an installation of hillside BMPs.
General Inspection8/24/20188/24/20188/24/2018PPASS
DetailsMichael Zawacki
Rock entrance installed at Holcomb. Water tank and truck on site. Looks like dust at distance but is actually diesel exhaust. Some dust being kicked up even with ground visibly saturated. No entrance on Tiger Lilly, workers are parking on the road.
Site Preparation8/22/20188/22/20188/24/2018PPEND
DetailsAndy J. Long
WIP
Conference8/22/20188/22/20188/22/2018PDONE
DetailsAndy J. Long
Onsite conference conducted 8/13 to discuss BMP installation and project prior to ESC & GRD being issued.