Permit Information
Permit NumberESC18-01022
StatusIssued
Name JILL JENKINS
Site Address 1995 W WINTER CAMP DR
Project NameEyrie Canyon Phase #10
Customer Number 
ePlanReviewNo
Description
Rough grading and subdivision infrastructure for Eyrie Canyon Phase #10. Certified stormwater designated. ESC site preparation inspeciton is required for initial BMPs: heavy duty construction entrance, heavy duty safety fence (not an ESC control) on southern limits, water tank for fugitive dust control, berms to contain and direct stormwater runoff to streets, silt fence to be installed at bottom of site behind sediment basin/retention pond and in between Stewart Gulch/Sand Creek. CGP eNOI filed and active, see # IDR10001AM. Additional BMPs may be required to be added at the discretion of City of Boise ESC Inspectors.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
General Inspection7/31/20207/31/20208/3/2020 PASS
DetailsMichael Zawacki
All disturbed areas have now been hydroseeded.
General Inspection7/16/20207/16/20207/16/2020 PASS
DetailsMichael Zawacki
Crew on site raking bank of pond getting it ready for final seeding.
Eyrie above vulture has been landscaped on south side. No grass is growing, trees have been planted.
Common area at Eyrie and wintercamp has topsoil spread.
No issues with any building lots.
General Inspection7/1/20207/1/20207/1/2020PPASS
DetailsMichael Zawacki
New storm water piping in lots has been installed. Buffer wasn't damage. RP was going to double check lots.
Landscapers on site starting to plant trees.
General Inspection6/24/20206/24/20206/24/2020PPASS
DetailsMichael Zawacki
Crew on site replacing stormwater line to a bigger size. RP weill check it out and add bmps as needed. Rest of area is vegetated.
General Inspection6/8/20206/8/20206/8/2020PPASS
DetailsAndy J. Long
BMPs installed and operable.

No violations observed, no corrections requested.

Landscaping crew onsite weeding and cutting vegetation and invasive thistle on slope next to Eyrie Way.
General Inspection5/28/20205/28/20205/29/2020PPASS
DetailsAndy J. Long
BMPs installed. Maintenance and clean up performed on lined washout pit that the subdivision is providing for homes active in phase 9.

No violations observed, RP notified that site will be working on noxious weed control of scotch thistle in the revegetated sections of phase 10 along the south side of Eyrie Way.

Conference5/21/20205/21/20205/21/2020APASS
DetailsMichael Zawacki
WIP on cleaning sidewalks and installing wattles.
Colin will come repair berms and add new containment further back when dried. will clean sediment from pond.
Pond will be finished when dry enough to install all riprap.
Conference5/21/20205/21/20205/21/2020ACANC
DetailsAndy J. Long
General Inspection5/20/20205/20/20205/20/2020PPART
DetailsMichael Zawacki
One berm failure at Eyrie and wintercamp, RP notified.
General Inspection5/14/20205/14/20205/14/2020 PASS
DetailsMichael Zawacki
No issues with development. Hillside have good growth, no runoff onto roads or sidewalk. Pond still not completed.
General Inspection4/29/20204/29/20205/1/2020 PASS
DetailsMichael Zawacki
Very little water in retention pond. Load of riprap delivered at bottom for pond.
No runoff onto road, no issues at site.
General Inspection4/14/20204/14/20204/14/2020 PASS
DetailsMichael Zawacki
No issues at site, lots are all stable.
Hiking path carved out of hillside.
General Inspection3/30/20203/30/20203/31/2020PPASS
DetailsAndy J. Long
.
General Inspection3/16/20203/16/20203/19/2020PPASS
DetailsMichael Zawacki
New trail cut into middle of hillside. Crew repairing sidewalks at bottom of goshawk.
Conference3/4/20203/4/20203/4/2020PPASS
DetailsMichael Zawacki
Collin has meeting with Veasy scheduled for site. Will go over which areas need to be reseeded.
Retention pond isn't ready and wont be seeded, needs ACHD approval, also neededs to put in walking path for HOA to get final plat approval.
Plan is to seed new disturbed areas and section where seeding didn't take.
General Inspection2/21/20202/21/20202/21/2020 PASS
DetailsMichael Zawacki
While at site crew showed up and started removing section of sidewalk.
General Inspection2/6/20202/6/20202/6/2020 PASS
DetailsMichael Zawacki
Lots are holding their water, little flow into pond. Dirt onb road and sidewalk has been cleaned and/or washed away.
General Inspection1/22/20201/22/20201/27/2020 PASS
DetailsMichael Zawacki
No blow outs from any lot. Road and sidewalk clean. Water in pond at bottom. Crew with mini excavator doing some work on entrance at washout area.
Tracking Control1/3/20201/7/20201/7/2020APASS
DetailsMichael Zawacki
Rp was at site cleaning over weekend.
Removed dirt ramp to washout, washout to be relocated off spur down road. Collin is getting rocks for entrance.
Gutters swept, will get sweeper to site.
General Inspection1/3/20201/3/20201/3/2020 FAIL
DetailsMichael Zawacki
Muddy entrance to washout. Lots of trackout.
RP already knows, Collin was supposed to have ordered rock and be up today to clean.
Lots have been bermed, plan on hydroseeding behind sidewalks.
General Inspection12/19/201912/19/201912/19/2019PPASS
DetailsMichael Zawacki
Main road paved top to bottom. Rings for manhole covers poured. Curbing completed. Crews on site prepping sidewalk pad and trying to warm ground with blankets. Some dirt moving activity on top.
General Inspection12/13/201912/13/201912/13/2019PPASS
DetailsMichael Zawacki
Road paved top to bottom.
Owners of denied development were on their parcel in Jeeps. No trackout. Talked to RP about an entrance and keeping roads clean.
General Inspection12/9/201912/9/201912/9/2019PPASS
DetailsMichael Zawacki
Grader finishing at bottom of road, no blowouts from site. Paver and crew at top getting machine dialed in and starting to lkay some asphalt.
Small section at top of Accinpinter paved
Track steer scraping mud of road..
General Inspection12/4/201912/4/201912/4/2019 PASS
DetailsMichael Zawacki
Talked to Collin at site. Area is being prepped for paving, contractor says they can get it done. Will need to follow up.
Conference11/5/201911/19/201911/21/2019ADONE
DetailsAndy J. Long
winterization conference 1:30; conducted Tuesday 11/19

Will install large lined berm at bottom of road to direct all runoff into the retention pond. Pond overflow to be capped and pond level monitored.

Additional lot soil roughening and berms to be added on lots along Eyrie. Upper area should remain undisturbed other than some stormwater volume and velocity controls

RP had wattles installed around the disturbed area from recent utility work and will be hydroseeded.

Lots above Arrow Villa should not hold water close to the ridge above existing homes, but should allow water to flow towards the unfinished road for storage and infiltration there.

No violations observed, RP requested curbing crew to demand concrete truck drivers use lined washout facility for all washout activiities.
General Inspection11/5/201911/8/201911/7/2019PCANC
DetailsAndy J. Long
Conference10/30/201911/5/201911/5/2019PCANC
DetailsAndy J. Long
1:30 PM lower entrance

winterization

rescheduled to 11/19 to check on site after road and sidewalks are installed.
General Inspection10/17/201910/17/201910/17/2019PPASS
DetailsMichael Zawacki
Track Utilities on site.
Material being stockpiled for road bed. Still plan on paving this year.
Pond will need to be cleaned, plan is to add inlet and outlets when paved.
RP wants to have a meeting on site to go over winter stabalization.
General Inspection10/2/201910/2/201910/2/2019PPASS
DetailsMichael Zawacki
WIP on joint trench. Talked to RP and she thinks they should be able to pave this fall.
Work on section of road leading to phase 8 where the bollards use to be. Widening and adding sidewalks per ACHD, also some repair at bottom.
General Inspection9/26/20199/26/20199/26/2019PPASS
DetailsAndy J. Long
Construction entrances installed. Permit information posted. No trackout or discharges. No fugitive dust. Water & sewer installed, Track Utilities onsite doing joint trench work.

WIP on extending Arrow Villa to Winter Camp adjacent to site.

No corrections at this time.
General Inspection9/17/20199/17/20199/17/2019PPASS
DetailsMichael Zawacki
No new activity. No runoff from site, all water obsorbed or directed into pond.
General Inspection9/10/20199/10/20199/10/2019PPASS
DetailsMichael Zawacki
Post rain inspection.
Site was able to handle all water, no discharged. Pond on bottom is connected to site.
Ran into Dean with Superior on site. Is waiting for joint trench to do site work before any sidewalks or streets. Concern about being pushed back into weather. If site not done RP will need to make sure water is contained to site and doesn't follow unfinished roads off site.
General Inspection9/5/20199/5/20199/5/2019 PASS
DetailsMichael Zawacki
No activity. No blowing dust, trackout, or issues. Owner wants to pave site before winter.
General Inspection8/21/20198/21/20198/21/2019 PASS
DetailsMichael Zawacki
No workers on site, all equipment except one dump truck gone. Still some water pipe and precast vaults at site. Rock entrance installed, no blowing dust.
General Inspection8/6/20198/6/20198/7/2019 PASS
DetailsMichael Zawacki
Small crew at top of site. Lower section is not active. Damaged areas from draining pool have been fixed. No trackout or dust, few stockpiles on site. Hillside vegetation doing good, few spots will need repairs.
General Inspection7/22/20197/22/20197/22/2019PPASS
DetailsMichael Zawacki
Road closure still in place.
Entrance on top and bottom, both free from trackout.
Water truck working on site, no dust.
General Inspection7/11/20197/12/20197/12/2019APASS
DetailsMichael Zawacki
Site is clean and contained. Good entrances and top and bottom. WIP on sewer, hopes to have all utilities, sidewalk, and paving done by October 15th.
General Inspection7/2/20197/2/20197/2/2019PPASS
DetailsAndy J. Long
WIP on utility installation. No trackout. Permit info posted

Water truck on site for dust control. Storm drains on Eyrie have sediment protection.

No corrections requested.
General Inspection6/25/20196/26/20196/26/2019APEND
DetailsAndy J. Long
Site is mobilizing to install utiilities, complete Eyrie Way, and widen and complete Arrow Villa extension to Winter Camp to finish phase 10.

ESC corrections in progress, discussed with site RP who will notify operators and developer:
- install/improve lower and upper construction entrances with 50 ft min length and heavy duty rock. Sweep loose dust at entrances regularly to prevent windblow fugitive dust.
- ensure that water truck is onsite today to control fugitve dust as necessary along haul roads and on material stockpiles.
- post new ESC sign on both upper and lower entrance.

Other comments:
- all construction traffic that can safely enter site from the lower entrance or Arrow Crest should do so to avoid using Arrow Villa. Employees should park at bottom entrance, project managers should travel through construction site.
- Arrow Villa extension should remain closed to the public and other thru traffic until Eyrie Way is open.
Conference6/6/20196/11/20196/12/2019ADONE
DetailsAndy J. Long
10 AM with Jill and Superior

Crews to begin pipe work and road widening of Arrow Villa. BMPs will be controlloing fugitive dust with water trucks and watching vehicle speed through site.

Site working on access plan for hauling and staging material, concern that trucks will not make it on Arrow Ridge or through site. Plan should be to complete lower section of pipe at the Eyrie Way entrance and install a rock construction entrance so trucks and materials can be routed through here.

Hillside vegetation is growing well, no immediate corrections, but there are some rills/channels that need to be filled and top of slope diversion berms should be fixed to prevent water from running down over disturbed slopes.
General Inspection5/29/20195/29/20195/29/2019PPASS
DetailsMichael Zawacki
No water made it to pond, all absorbed by growing hillside vegetation. No major issues at site.
General Inspection4/30/20194/30/20195/6/2019PPART
DetailsAndy J. Long
Inspection conducted last Thursday 5/2 PM. No trackout or discharges from site.

No recent construction activity. Slope vegetation is growing well in most hydroseeded areas.

At time of inspection, corrective actions on the erosion on the slope at the bottom of the subdivsion above Eyrie Way entrance have not had any repairs or reinstallation of wattles. Site needs to install/improve berms and/or other controls at top of slope to prevent water from concentrating in existing rills down the slope.
- no corrections yet on erosion that occured on the terraced lots on north side of Eyrie Way
- Site will schedule pre-construction/ESC conference with Superior construction prior to their activation.
- Finish removing fence poles from the safety fence.

Corrections should be completed within the next two weeks.
General Inspection4/18/20194/18/20194/18/2019PPASS
DetailsMichael Zawacki
Grass starting to grow. No major issues.
Complaint Inspection4/15/20194/15/20194/15/2019PDONE
DetailsAndy J. Long
report of leaking pipe at entrance draining out of entrance area

Leaking pipe under HOA landscaping authority. Notified RP and HOA. Water has been turned off.
General Inspection4/9/20194/9/20194/9/2019APASS
DetailsMichael Zawacki
post rainfall inspection
Site is absorbing water, very little making it to retention pond. Not much grass growing. Some small rills beginning to form. No major issues.
Conference4/2/20194/2/20194/4/2019PDONE
DetailsAndy J. Long
Walk through inspection with RP conducted 4/2 AM

No trackout or discharges leaving site. Perimeter BMPs are in good condition, stormwater retained onsite. No construction activity. Site is revegetating and waiting for good conditions for installing road and sewer. Rough grading is complete.

Corrections to work on over next 2-3 weeks:

- schedule crew to remove orange safety fence and poles on ridge above Arrow Villa Drive
- make plan to restore areas of slope erosion, in particular at the bottom of ridge at subdivision at Eyrie Way and at the slope above Winter Camp @ Eyrie. Check to see if water can be diverted or retained with berms at top of slope to avoid running down steep slopes, rake out rills, repair damaged wattles, install more slope interupting wattles, investigate option to reseed, tacity, or use ECBs for stabilization of steep slopes.
- runoff from pre-existing drainage basins and sheet flow from parcels caused erosion of terraces on N side of Eyrie Way. Need to re-work berms on terraces and consider stabilizing/diverting/retaining water that runs on lots from surrounding draws.
- schedule pre-construction meeting with Superior Construction prior to mobilizing for infrastructure installation. Discuss construction access and staging area location.
General Inspection3/27/20193/27/20193/27/2019PCANC
DetailsAndy J. Long
General Inspection3/26/20193/26/20193/26/2019PPASS
DetailsMichael Zawacki
Will need to monitor hillside down by Villa Ridge. Looks like there has been seepage, some wattle failure and some spots look like sink holes opening on hillside. Best to stay off area until dry to avoid increasing damage risk.
General Inspection3/6/20193/7/20193/7/2019APASS
DetailsMichael Zawacki
No runoff or failures. All water contained on site.
General Inspection2/25/20192/25/20192/25/2019PPASS
DetailsMichael Zawacki
Water is pooling behind new rocks and discharging clear.
Pile of silt fence on sidewalk needs to be removed.
North facing areas are still snow covered.
General Inspection2/14/20192/14/20192/14/2019PPEND
DetailsMichael Zawacki
Met with Jill and Collin on site. Retention on bottom of road, not pond, overfilled. Some turbid discharge, goes to retention pond not creek. Washed gravel was ordered to make a berm and filter before road. Once dried berm on retention will be repaired and incresed in height.
General Inspection2/13/20192/13/20192/13/2019PPASS
DetailsMichael Zawacki
rainfall inspection.
No ESC issues, no dirt or turbid water leaving site.
General Inspection2/1/20192/1/20192/1/2019PPASS
DetailsMichael Zawacki
No major issues, nothing leaving site. Pile of old silt fence laying on sidewalk at bottom entrance.
General Inspection1/22/20191/22/20191/22/2019PPART
DetailsMichael Zawacki
RP on site cleaning mud from where builder got stuck trying to unload backfill. Sweeper scheduled for final cleanup.
Water in retention at bottom of hill. Hillsides on north facing slope need to be monitored for rilling.
General Inspection1/17/20191/17/20191/17/2019PPASS
DetailsAndy J. Long
BMPs working. No sediment runoff or hillside erosion observed. No corrections at this time
General Inspection1/10/20191/10/20191/10/2019PPASS
DetailsMichael Zawacki
Bollards have been removed, ecology blocks with chain have been put in their place. No mud leaving site on upper end. Retention built on bottom of road on lower section, very little water inside. Very little water in retention pond. No hillside failures.
General Inspection12/19/201812/19/201812/19/2018PPART
DetailsMichael Zawacki
Bollards have been ran over, curb broke, and some tracking.
Wire with survey tape has been strung across sledding hill and around upper area to try and keep people off. Hillsides are still stable, no runoff from bottom. Did not walk site due to mud.
General Inspection12/10/201812/10/201812/10/2018PPASS
DetailsMichael Zawacki
Site is all snow covered.
Sledders have gone down hill and ran over wattles. Talked to RP and they will try to figure a way to keep people off.
General Inspection11/14/201811/14/201811/14/2018PPASS
DetailsMichael Zawacki
Met with RP and did site walkthrough.
Wattle has been properly installed on slopes, trenched in and overlapped ends. One area towards bottom will need to be extended by 75', RP will take care of it.
VSI hydroseeding on site, starting on slopes with seed mulch and tackifier.
Conference11/2/201811/5/201811/5/2018APASS
DetailsAndy J. Long
1030 site walk though to review next steps after grading.

Site access will be blocked off to prevent incidental track out and trespassing. If access is required, rock construciton entrances will be needed.

Earthwork is nearly complete, on minor work remaining. Slopes have been horizontally tracked, parcels have retention berms installed to allow water to infiltrate on lots rather than runoff.

Slope interupting wattles are to be installed on the north facing slope on south side of entrance at Eyrie Way. 3-4 sections of wattles installed along contour, trench 2-3 ", and staked every 5 ft. Slope wattles are also required at the top of the site on the northwest side of Eyrie Way and Winter Camp. After wattle installation, hydroseed application will be completed on all disturbed areas including parcels. Both of these steps are to be implemented before the end of the week of Nov. 12-16th.

Runoff control berms will be installed on roadways approximately every 150 feet to slow down and retain runoff.

RP Jill to inspect and add additional wattles along the graded ridge in a few areas where the berm is not clearly above the parcel grade.

No trackout, discharges or other violations. Concrete washout for phase #9 SFHs is installed within the phase #10 footprint
Conference11/2/201811/5/201811/5/2018ACANC
DetailsMichael Zawacki
site walk through @1030
General Inspection11/2/201811/2/201811/2/2018PPASS
DetailsAndy J. Long
WIP on final stages of grading. Slopes are in process of horizontal tracking, an erosion control technique. No trackout or discharges off site.

Corrective actions:
- install wattle on section of berm on the cut ridge. Contact inspector for details.
- block entrances or get new construction entrance rock installed to prevent any trackout from crews and trespassers alike.
General Inspection10/17/201810/17/201810/17/2018PPASS
DetailsMichael Zawacki
Ran into RP doing inspection while on site. She will come Saturday to do some BMP modifications while workers are off. No dust while working. Some water in pond at bottom, looks like tank is being drained with hose. No trackout from lower entrance.
General Inspection10/10/201810/10/201810/10/2018PPASS
DetailsMichael Zawacki
post rainfall inspection
Knife River didn't work 10/9.
All BMPs worked and held up. No issues at site, no discharges.
General Inspection10/3/201810/3/201810/3/2018PPASS
DetailsAndy J. Long
WIP on grading and moving fill from ridge to lower areas of subdivsion phase. Water wagons circulating with belly scrapers, no fugitive dust clouds leaving site. NO trackout from site access points. A water diversion trench has been installed at botton of canyon and Eyrie Way to direct any runoff coming down into the stormwater/sediment retention pond.

Ridge work is being conducted per protocol, 2-3 foot shelf left to prevent and rockfall or clods from rolling down hill. Safety fence appears in good condition, area of slope disturbance from water truck misfire has had ECBs and slope interupting wattles installed.

Approved, site is in compliance.
General Inspection9/28/20189/28/20189/28/2018PPASS
DetailsMichael Zawacki
Lip on home side of hill, all operations are below that level. Water wagons on site, no dust. Lower entrance has barricades, no trackout at upper entrance.
General Inspection9/21/20189/24/20189/24/2018PPASS
DetailsMichael Zawacki
Work just getting started for morning. Water wagon is leading way with dozer using ripper tooth behind it. There is still a high berm between grading area and hillside, all workers in low area away from edge.
Pond at lower section has been enlarged, water tank stored above, will drain into retention if it fails. Silt fence on bottom, corner post has been broken in half. No trackout.
General Inspection9/19/20189/21/20189/21/2018ADONE
DetailsAndy J. Long
Safety protocol for grading on hillside has been updated and a safety inspection log book created. No new corrections. Inspection scheduled for Monday.
Complaint Inspection9/19/20189/19/20189/19/2018APASS
DetailsMichael Zawacki
Met with Adam, superintendent of site and did walk through. He has crew walking fence line and taking pictures for time stamp proof of inspection.
Excavators are cutting down inside of hill and leaving a bench. Site foreman is running the smaller D6 dozer in mornings to level out cut. Dozer is running parallel to hillside with spotter. Dozer being used has ability to angle blade and is pushing everything away from homes and into downhill side of ravine. From bottom of hill may be difficult to see what work is actually being done and may look like a flat cut not being angled. All of area is sloped toward ravine like discussed, no major rockfall towards barrier fence seen.
BMP Violation9/17/20189/18/20189/18/2018APEND
DetailsAndy J. Long
corrections still in progress.

Stockpile/pushed up dirt at top of the hill where grasses and mud were washed down hill has been removed. Fence section that captured mud has been cleaned off. Will potentially need further cleanup and fastening to the ground . Debris captured should not be left in a pile but spread up and down the disturbed slope and prepped to receive hydroseeding.

Heavy duty wattles have been installed, but need to be staked in. Slope will have erosion control blankets installed this week or next.
Complaint Inspection9/17/20189/17/20189/17/2018PFAIL
DetailsAndy J. Long
Report of landslide received. Incident reported via email on 9/15 PM.

Inspection conducted 9:15 AM Monday 9/17.

Earth work subcontractor L3 had a water truck working on Saturday morning 9/15 to soak water in on the area of planned excavation on Monday. Plan was to get ahead of fugitive dust and make the material more easy to grade/doze. Water truck driver did not observe equipment limits toward the edge of rim at got stuck in the mud while spraying water inadvertantly over the berm and down the slope towards Arrow Villa. Force of the water spray caused uprooted grass and mud to flow down a previous compacted area (equipement tracks from 2-3 years ago). The rockfall safety fence stopped a majority of mud and debris. Some water and mud did flow under the fence down to the toe of the slope depositing sediment in the pond. Does not appear any water flowed further into pond towards pond outlet.

Corrections:
- remove captured mud and debris and fix fence. Re-secure fence posts and staples on either side of where the mud is located. Rake out compacted mud channel.
- remove any stockpiles or pushed up dirt from edge of rim
- install temporary sediment control and slope interupting wattles on the eroded area. In 1-2 weeks the slope shall be tracked and hydroseeded. Requested that permission be obtained through ACHD.
- remove deposited sediment in the edge of pond area at bottom of slope (approximately 1/3 of a cubic yard)

- no further advance soaking into the ridge is allowed. Water trucks and other equipment are restricted from working or driving directly upon the edge. L3 is to delineate this restricted area. Water truck operator is no longer to work unless on L3 field supervisor is on duty.

- each day a safety meeting and onsite supervisor (Taylor or Adam with L3) shall walk the area of work and fence sections to inspect potential issues. Additionally the rim should be inspected at the end of each activie work day to make sure there is no ponding, low spots, or loose rock or clods that could potentially roll down hill.

- All grades (including temporary) on the rim shall be done in a way that directs & drains water away from the slope on the south side of the rim and towards the north to the valley area of phase 10.
General Inspection9/11/20189/13/20189/14/2018APASS
DetailsAndy J. Long
Inspection conducted 9/13 2:00 PM

No trackout, discharges, or fugitive dust leaving site. BMPs on perimeter are installed (stormdrain protection, silt fence). Construction entrance is currently closed for future utilitiy work. Minimal access allowed until heavy duty rock entrance can be re-installed. Crews park off the dirt up on Winter Camp.

Sediment basin and future stormwater pond has been excavated. Need to make sure the sides have been properly tracked (perpindicular to slope)

Now that stormwater pond is availalbe, next week we need to make sure any drainage from the south ridge goes to the pond rather than flowing to Eyrie Way.

No corrections for violations. Follow up next week.
General Inspection9/6/20189/6/20189/6/2018PPASS
DetailsMichael Zawacki
Grading has begun above the lower homes and down the canyon. Lots of dust on top, falling into draw away from homes, water wagon is spraying site. Still a large buffer and no grading on the downhill slope torwards homes.
No issues at lower entrance.
General Inspection8/28/20188/30/20188/30/2018PPASS
DetailsMichael Zawacki
Grading has begun around intersection of Winter Camp & Eyrie. Water tank is set, water is being sprayed on area. Some dust from operation grading down hill, using belly loaders to transport to low area. Dust isn't constant but is noticeable.
SWPPP map posted on board at lower entrance with RP contacts and permit.
General Inspection8/29/20188/29/20188/29/2018ACANC
DetailsAndy J. Long
data entry error
Site Preparation8/28/20188/28/20188/28/2018PPASS
DetailsAndy J. Long
Construction entrance, storm drain inlet protection, permit signage, and silt fence barrier and buffer in place (inspected 8/27). Safety fence installed 20 ft down slope for the post graded edge of hill, approximately 10 vertical feet. Full installation to be completed prior to approval to begin earthwork. First area of disturbance will be to dig the stormwater pond/sediment basin.




- Bottom edge flap of safety fence has been secured with 6" staples as requested

- extra fence posts in areas where poles are in loose ground have been added to increase fence strength

- concrete barricades placed @ the lower bollards. Signage to restrict/direct construction traffic from using Arrow Villa Rd.will be posted

- water tank and truck are now onsite for dust control. Tank surrounded by secondary containment berm to prevent leaks from running down hill or to the road.

Excavation work will begin tomorrow. Approved for construction.




General Inspection6/15/20206/15/2020 P 
DetailsAndy J. Long
post rainfall inspection