Information based on query as of Friday, May 17, 2024.
Permit Information
Permit NumberESC15-00094
StatusFinaled
Name ERIC ALLEN
Site Address 3299 E WINDSONG DR
Project NameBoulder Heights No 6
Customer Number 
ePlanReviewNo
Description
New hillside subdivision phase grading and development project. Project scheduled 3/2/2015 - 9/1/2015. JH Development and Central Paving are operators. Perimeter controls and stabilized construction access must be installed prior to construction. SWPPP states lined leakproof washout containment will be use for concrete washout. Site preparation/pre-construction meeting is required.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
General Inspection3/5/20193/5/20193/5/2019 CANC
DetailsMichael Zawacki
DOC - Permit Finaled3/5/20193/5/20193/5/2019PPASS
DetailsMichael Zawacki
Neighborhood nearly completed and landscaped. Stormwater all contained. Lots being built are responsible for their own BMPs.
General Inspection2/18/20192/18/20192/19/2019 CANC
DetailsAndy J. Long
General Inspection2/1/20192/1/20192/1/2019 CANC
DetailsAndy J. Long
General Inspection1/17/20191/17/20191/17/2019 PASS
DetailsMichael Zawacki
Lot about half landscaped, crews on site. All materials have been removed from road and sidewalk.
General Inspection12/31/201812/31/201812/31/2018 PASS
DetailsMichael Zawacki
Most homes complete, each lot responsible for their own BMPs
General Inspection12/14/201812/14/201812/14/2018 CANC
DetailsAndy J. Long
Site Final11/29/201811/29/201812/3/2018PNR
DetailsAndy J. Long
snow covered. Will wait till spring to assess vegetation. No issues observed.
General Inspection11/29/201811/29/201811/29/2018 CANC
DetailsAndy J. Long
General Inspection11/14/201811/14/201811/15/2018 PASS
DetailsMichael Zawacki
Sprinkler & landscaping company on site. Most exterior home work complete.
General Inspection10/30/201810/30/201810/30/2018 CANC
DetailsAndy J. Long
General Inspection10/15/201810/15/201810/15/2018 CANC
DetailsAndy J. Long
General Inspection9/28/20189/28/20189/28/2018 CANC
DetailsAndy J. Long
General Inspection9/13/20189/13/20189/13/2018 PASS
DetailsMichael Zawacki
General Inspection8/29/20188/29/20188/31/2018 CANC
DetailsAndy J. Long
General Inspection8/14/20188/14/20188/14/2018 PASS
DetailsMichael Zawacki
Neighborhood clean, homes responsible for their own BMPs.
General Inspection7/30/20187/30/20187/30/2018 PASS
DetailsMichael Zawacki
Neighborhood is clean. Homes under construction all have their own BMPs. There are no neighborhood specific BMPs.
General Inspection7/13/20187/13/20187/13/2018 PASS
DetailsMichael Zawacki
WIP on a few homes. Builders are responsible for their own BMPs
General Inspection6/28/20186/28/20186/28/2018 PASS
DetailsMichael Zawacki
Few homes under construction. No ESC issues in neighborhood. Each home is responsible for their own BMPs.
General Inspection6/13/20186/13/20186/15/2018 CANC
DetailsAndy J. Long
General Inspection5/29/20185/29/20185/29/2018 CANC
DetailsAndy J. Long
General Inspection5/14/20185/14/20185/14/2018 PASS
DetailsMichael Zawacki
Neighborhood in good shape. Few homes causing a little mess. Individual homes had inspections logged.
General Inspection4/27/20184/27/20184/27/2018 CANC
DetailsAndy J. Long
General Inspection4/12/20184/12/20184/12/2018 CANC
DetailsAndy J. Long
General Inspection3/28/20183/28/20183/28/2018 PASS
DetailsMichael Zawacki
Few homes under construction. Neighborhood is clean, no ESC issues.
General Inspection3/13/20183/13/20183/14/2018 PASS
DetailsMichael Zawacki
No building lots causing issues after rain event.
General Inspection2/26/20182/26/20182/27/2018 CANC
DetailsAndy J. Long
General Inspection2/9/20182/9/20182/9/2018 CANC
DetailsAndy J. Long
General Inspection1/25/20181/25/20181/25/2018 PASS
DetailsMichael Zawacki
Mostly complete. Few vacant lots, some homes being built. Neighborhood is clean. Home builders are responsible for their own sites.
General Inspection1/10/20181/10/20181/10/2018 PASS
DetailsMichael Zawacki
Some WIP on homes, few vacant lots, few lots started and abandoned. Neighborhood BMPs still installed. Homes also have their own BMPs. No issues observed.
General Inspection12/26/201712/26/201712/26/2017 CANC
DetailsAndy J. Long
Random Inspection12/11/201712/11/201712/11/2017PPASS
DetailsMichael Zawacki
General Inspection11/27/201711/27/201711/27/2017 PASS
DetailsAndy J. Long
General Inspection11/10/201711/10/201711/13/2017 PASS
DetailsMichael Zawacki
WIP on SFH. Vacant lots are vegetated and no dirt or runoff.
General Inspection10/26/201710/26/201710/27/2017 CANC
DetailsAndy J. Long
General Inspection10/11/201710/11/201710/11/2017 CANC
DetailsAndy J. Long
General Inspection9/26/20179/26/20179/28/2017 PASS
DetailsAndy J. Long
WIP on SFHs in BH#5. No hillside erosion, sediment runoff issues or other issues. No corrections.
General Inspection9/11/20179/11/20179/19/2017 CANC
DetailsAndy J. Long
General Inspection8/25/20178/25/20178/25/2017 PASS
DetailsAndy J. Long
No subdivision development activity. No BMP maintenance required at this time. Slopes are well vegetated with limited sediment runoff. No corrections. Multiple SFHs in progress permitted seperately.
General Inspection8/10/20178/10/20178/14/2017 CANC
DetailsAndy J. Long
General Inspection7/26/20177/26/20177/26/2017 CANC
DetailsAndy J. Long
General Inspection7/11/20177/11/20177/11/2017 CANC
DetailsAndy J. Long
General Inspection6/26/20176/26/20176/26/2017 PASS
DetailsAndy J. Long
WIP on SFHs within BH#6 phase are in compliance and permitted seperately.

No hillside erosion issues occuring and vegetatation has established. Storm drains have coir fiber filter mats installed. No corrections requested at this time.
General Inspection6/9/20176/9/20176/9/2017 CANC
DetailsMelissa Jannusch
General Inspection5/25/20175/25/20175/25/2017 CANC
DetailsAndy J. Long
General Inspection5/10/20175/10/20175/10/2017 CANC
DetailsAndy J. Long
General Inspection4/25/20174/25/20175/1/2017 CANC
DetailsAndy J. Long
General Inspection4/10/20174/10/20174/11/2017 CANC
DetailsAndy J. Long
General Inspection3/24/20173/24/20173/24/2017 CANC
DetailsAndy J. Long
General Inspection3/9/20173/9/20173/9/2017 PASS
DetailsMelissa Jannusch
No trackout. No ESC issues.
General Inspection2/22/20172/22/20172/24/2017 PASS
DetailsMelissa Jannusch
WIP on some SFH. No ESC issues noted.
General Inspection2/7/20172/7/20172/8/2017 CANC
DetailsMelissa Jannusch
General Inspection1/23/20171/23/20171/26/2017 CANC
DetailsAndy J. Long
General Inspection1/6/20171/6/20171/10/2017 CANC
DetailsAndy J. Long
General Inspection12/22/201612/22/201612/29/2016 CANC
DetailsAndy J. Long
General Inspection12/7/201612/7/201612/9/2016 CANC
DetailsAndy J. Long
General Inspection11/22/201611/22/201611/23/2016 PART
DetailsAndy J. Long
Hillsides in good conditions, no sediment runoff areas or rills observed.

Correciton:
- need to sweep and shovel accumulated materials in gutters at inlets with filter mats.
General Inspection11/7/201611/7/201611/7/2016 PASS
DetailsEric Strole
General Inspection10/21/201610/21/201610/24/2016 PASS
DetailsAndy J. Long
General Inspection10/6/201610/6/201610/6/2016 PASS
DetailsAndy J. Long
No new subdivision activity on this phase. No hillside erosion or runoff issues occuring. Unbuilt lots have vegetative stabilization. Several SFHs active at top of Windsong & Echo Ct as BH phase # 6 construction.
General Inspection9/21/20169/21/20169/21/2016PPASS
DetailsAndy J. Long
New coir mat sediment filters installed on inlets at Birdsong and Windsong. Windsong was recently swept. SFH activity occuring at top of hill as well as BH#6.No hillside erosion issues observed.
Site Final9/2/20169/9/20169/9/2016PCANC
DetailsAndy J. Long
no site final, data entry error
General Inspection9/2/20169/2/20169/2/2016 PART
DetailsAndy J. Long
No new subdivsion development work. SFHs permitted seperately and are in good condition.

Correction request to Eric:
- replace damaged filter mats on all inlets on Windsong and Birdsong next week.

RP agreed to correction. Will check next check to verify.
General Inspection8/18/20168/18/20168/18/2016PPART
DetailsAndy J. Long
Need to conduct maintenance on all storm drain coir filter mats; install new material. Requesting homebuilders to remove soiled and degraded ones when they complete projects. Verbal request to Eric
General Inspection8/9/20168/9/20168/9/2016 PASS
DetailsAndy J. Long
3 active homes in progress at top of Windsong and on Echo culdesace. No subdivision work. No hillside erosion areas of concern and crews are working on storm drain sediment filters and sweeping.
General Inspection7/25/20167/25/20167/25/2016 PASS
DetailsEvan Jenkins
General Inspection7/8/20167/8/20167/8/2016 PASS
DetailsAndy J. Long
Slopes stabile, no sediment runoff or hillside erosion issues observed. 2 SFHs in progress. BMPs installed, no violations installed.
General Inspection6/23/20166/23/20166/23/2016 PASS
DetailsEvan Jenkins
2 SFHs now in progress with individual washout containment. DIs in BH#6 have fiber sediment control mats. Subdivsion grading is complete, no areas of sediment runoff or hillside erosion.
General Inspection6/8/20166/8/20166/8/2016 PASS
DetailsAndy J. Long
No subdivision or SFH actvity at this time. Should see new homes starting soon. No ESC issues. No corrections.
General Inspection5/24/20165/24/20165/24/2016 PASS
DetailsEvan Jenkins
General Inspection5/9/20165/9/20165/9/2016 PART
DetailsEvan Jenkins
sweep street, curb and gutter. sheet runnoff from fridays rain event caused issues
General Inspection4/22/20164/22/20164/22/2016 PASS
DetailsAndy J. Long
No subdivision activity. BMPs in good condtions, no corrections requested.
General Inspection4/7/20164/7/20164/7/2016 PASS
DetailsAndy J. Long
No activity. No SFHs in progress yet. Hillsides have slope interuption and sediment control wattles and areas have been hydroseeded last fall. No erosion issues or sediment runoff occuring. Site in currently in condition. BH #7 is in progress up above the site.
General Inspection3/23/20163/23/20163/23/2016 PASS
DetailsAndy J. Long
Hillside BMPs and hydroseeding applied last fall are working well to keep sediment on site. No corrections needed at this time. BH#7 to start soon, see ESC16-00225
General Inspection3/8/20163/8/20163/8/2016 PASS
DetailsAndy J. Long
Hillsides in good condition. No significant or observable erosion rills or gullies. BMPs installed in areas of risk. No sediment blow outs or evidence of turbid dishcarges. No corrections at this time.
General Inspection2/22/20162/22/20162/22/2016 PASS
DetailsEvan Jenkins
General Inspection2/5/20162/5/20162/5/2016 PASS
DetailsAndy J. Long
Boulder Heights in good condition. Sediment staying onsite, BMPs currenty effective. No issues. No construction activitiy. Will need to hydroseed open areas not slated for SFH construction to stabilize hillsides.
General Inspection1/21/20161/21/20161/22/2016 CANC
DetailsAndy J. Long
General Inspection1/6/20161/6/20161/7/2016 PASS
DetailsAndy J. Long
No activity. Hillside BMPs working well to keep sediment and topsoil in place. Sand on road is from winter safety applications. No corrections needed at this time.
General Inspection12/22/201512/22/201512/22/2015 PASS
DetailsAndy J. Long
Hillside BMPs such as horizontal tracking, incremental wattle installations to shortening slope lengths, sediment trap berms are working well on the site. Some areas have started to vegetate where hydroseeding occured.

No erosion or sediment discharges offsite observed. Approved.
Random Inspection12/7/201512/7/201512/7/2015PPASS
DetailsAndy J. Long
BMPs and site grading practice has worked well to keep sediment and slopes stabile in BH#6. No BMP failures identified. No significant rills or gullies observed. Wattles and sediment trenches installed incrementally on slopes has helped considerably. Approved.
General Inspection11/30/201511/30/201511/30/2015 PASS
DetailsAndy J. Long
No activity. No runoff occuring due to frozen conditions. BMPs and slope stabilization practices have been implemented. Will check performance at end of week when temperatures are forecasted to increase with chance of rain.

No corrections at this time.
General Inspection11/13/201511/13/201511/13/2015 PASS
DetailsEvan Jenkins
No discharges leaving the site. A series of BMP's (Straw and Composted Waddles) throughout project along with Drop Inlet Protection. No issues observed at this time
Random Inspection10/29/201510/29/201510/29/2015PPASS
DetailsAndy J. Long
No issues at site, no discharges, sediment/mud blowouts to roadways, or other issues. The slopes in Boulder Heights #6 were hydroseeded on Tuesday 10/27. Wattles are installed on long slopes to treat sheet flow for sediment.

Stockpile of topsoil on Echo is still there, will continue to check with Gossett landscaping project for removal and cleanup of culdesac.
Conference10/22/201510/23/201510/23/2015APART
DetailsAndy J. Long
Landscaping crew access backyard of home through open area of BH#6 off Echo culdesac causing some trackout. Topsoil stockpiled adjacent to sidewalk,

Warning and request issued to onsite foreman of irrigation installation company to clean up mud clud and tracks on sidewalk and gutter. Also to sweep up and contain stockpile.

Project management is by Gossett Landscaping.
Conference10/21/201510/22/201510/22/2015ACANC
DetailsAndy J. Long
rescheduled with RP.
General Inspection10/21/201510/21/201510/21/2015 PASS
DetailsAndy J. Long
No sediment runoff from recent rainfall observed, or it has been cleaned. Hill slopes are currently free of significant erosion rills or gullys and wattle BMPs are installed and the hill was tracked/roughed to slow and contain runoff.

No corrections at this time, will investigate seperate home remodel contractor causing issues of Echo culdescac tomorrow AM.
General Inspection10/2/201510/2/201510/2/2015 PASS
DetailsAndy J. Long
No activity currently. Lots prepared for building. Cut hillsides have been compacted & tracked. Perimeter and incremental wattles have been installed for sediment control. No issues at site. No SFHs currently in progress.
Random Inspection9/17/20159/17/20159/17/2015PPASS
DetailsAndy J. Long
Checked unvegetated and recently graded hillsides for erosion and sediment runoff. Hillside slope tracking, compaction, and placement of wattles seems to have contained sediment on site except in one small area.

Some maintenance and cleanup will be necessary but site BMPs performed well considering the intensity and duration of rainfall.
General Inspection9/11/20159/11/20159/11/2015 PASS
DetailsAndy J. Long
Site currently inactive. Hillsides have been tracked, roads, gutters, and storm drains installed. Temp BMPs installed on sections of long slope to capture sediment.
Random Inspection8/27/20158/27/20158/27/2015PPASS
DetailsAndy J. Long
No activity in new phase of Boulder Heights. Roads, gutters, and utilities are complete.

Hillside that were graded have been properly tracked horizontally and temporary erosion control and sediment containment wattles have been installed. No rill or gully erosion observed. No loose sediment on hard surfaces. Approved.
General Inspection8/18/20158/18/20158/18/2015 PASS
DetailsEvan Jenkins
Road and sidewalks along with curbs complete.
A series of straw waddles and gator guards are installed throughout the project. No trackout or discharges occuring
General Inspection7/29/20157/29/20157/29/2015 PASS
DetailsEvan Jenkins
Prepping for paving. No trackout out occuring at this time.
Tracking Control7/10/20157/13/20157/13/2015APASS
DetailsAndy J. Long
Areas affected by sediment deposits have been swept. Additional controls installed. Road will soon be paved.

Sweeper still onsite to clean another time. No new corrections.
Tracking Control7/10/20157/10/20157/10/2015PPEND
DetailsAndy J. Long
Clean up and additional sediment controls are being installed along slopes that have sheet flow that concentrates at Windsong. Sand and gravel from the prepped road base have migrated down hill. 2 sweepers and skidster are on site. Response has been proactive.

Walked the site, no significant hillside rills or gullies observed. Upper portion abutting existing homes did not have issues and sediment control wattle and buffer were effective.

Preparing for more rainfall this weekend.
General Inspection7/9/20157/9/20157/9/2015PPASS
DetailsAndy J. Long
Inspected perimeter after > 0.25 rain event. Sediment traps on Windsong appear to have collected a decent amount of sediment and no rills or blowouts are visible. No significant trackout from vehicles. Approved - will remind RP to clean out sediment traps (sandbag wedges)
Random Inspection7/1/20157/1/20157/1/2015PPASS
DetailsAndy J. Long
No significant trackout at upper and lower entrances to new subdivision phase. Some dust due to unloading but not crossing property lines at time of inspection and no neighbor complaints received.

Will continue to monitor. No corrections issued at this time. Central Paving crews are onsite.
General Inspection6/19/20156/25/20156/25/2015APASS
DetailsAndy J. Long
Follow inspection from corrections issued 6/19

Entrance has been swept as requested. No activity. No dust or other issues observed. Approved.
Complaint Inspection6/19/20156/19/20156/19/2015APART
DetailsAndy J. Long
RP from JH Development reported a complaint he received regarding BMPs at Boulder Heights #6

Site is currently inactive and will be for the next 3-4 weeks, when Central Paving will return to complete work.

New BMPs installed include:
- J shaped sandbag sediment containment at Windsong and Birdsong
- Restricted entrance; using paved surface as stabilized entrance and closed Windsong at Birdsong
- Wattle was maintained at SE limit of disturbance to contain sheet flow sediment. No issues or breeches observed.

Corrections needed:
1. Install filter or manhole plugs to keep dirt out of sewer on Windsong entrance
2. Move stockpile away from manhole and street
3. Perform sweeping and cleaning of the sidewalk, street, and gutter on the paved portion of Windsong.
4. Pick up any litter on site
5. Install wattle above newly constructed drainage pipe outlet and rip rap to contain sediment from the distuberd area of the outlet.

Overall site is in good condition, no significant trash issues, no trackout, no fugitive dust occuring.

Will reinspect end of next week 6/25
General Inspection5/13/20155/13/20155/13/2015PPART
DetailsAndy J. Long
Upper entrance is still closed off to prevent trackout in multiple areas. Joint-trenching for utilities is occuring next to entrance on Windsong.

Site retained sediment and contours and berms disperse runoff in several areas, preventing offsite discharges.

1 correction:
Sweep up existing trackout at end of week. Correction discussed with RP.
General Inspection4/29/20154/29/20154/29/2015PPART
DetailsAndy J. Long
WIP. Preparing

Requesting that sediment containment BMPs or check dams be used to treat runoff down Windsong. Receiving DI on Windsong needs new inlet protection.

No significant trackout or fugitive dust occuring. Need to prepare bottom of site for rain events to treat sediment runoff.
General Inspection4/1/20154/1/20154/2/2015PPART
DetailsAndy J. Long
WIP on grading future roadway area in Boulder Heights #6. Upper access points are blocked off to prevent unauthorized access and prevent trackout. No dust; work staying within limits of disturbance.

Corrections to be completed by next week:

1. Install check dams in along the construction entrance where runoff channels down.
2. Install new heavy duty rock construction entrance
3. Install sediment basin or other BMP for sediment control for upper disturbed slope runoff occuring above the stormwater pond.

Will check back next week. Verbal corrections given to RP.

General Inspection3/30/20153/30/20153/30/2015PPASS
DetailsAndy J. Long
BH#5 in progress. Currently excavatiing and hauling dirt offsite. Construction entrance installed, permit and SWPPP on site. No trackout or discharges. Truck drivers moving slowly to keep dust down - no issues at time of inspection.
Site Preparation3/11/20153/12/20153/13/2015APEND
DetailsAndy J. Long
New grading map and ESC site map are not available due to City network issues, but permit has been issued and eNOI already filed.

SWPPP is onsite, City of Boise permit posted, and downhill inlets have protection.

No grading work is to occur until plans are released and site prep inspeciton is conducted next week.

No issues at site, current work of moving the stockpile areas is done under ESC !4-00381
Site Preparation3/11/20153/11/20153/11/2015PNR
DetailsAndy J. Long
Boulder Heights # 6

Work on moving stockpile under ESC14-00381. Need to install BMPs for subdivision work.