Permit Information
Permit NumberESC17-00078
StatusIssued
Name RENATO JUAREZ
Site Address 2570 E WARM SPRINGS AVE
Project Name 
Customer Number 
ePlanReviewNo
Description
Warm Springs Village. Site preperation and installation of BMPs required before earth work. BMPs include: Stabilized construction entrance, staging area, silt fence at south west side of site, and fiber rolls along warm springs ave. Ensure DI bags are in place once SWMS is in use.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Site Final8/7/20208/12/20208/12/2020PNR
DetailsAndy J. Long
Two homes still in progress on Boulder View with dumpster and landscaping. Will request DI removal after complete.
General Inspection8/7/20208/7/20208/7/2020 CANC
DetailsAndy J. Long
General Inspection7/23/20207/23/20207/24/2020 PASS
DetailsAndy J. Long
Last two homes being landscaped. Next inspection will check for DI bags which will need to be removed. Activity is on the east end of Boulder View. No violations observed.
General Inspection7/8/20207/8/20207/8/2020 PASS
DetailsMichael Zawacki
Almost all homes now completed and landscaped. Site is clean.
General Inspection6/23/20206/23/20206/23/2020 PASS
DetailsAndy J. Long
All homes near completion. Will have DI bags removed and should be able to close permit.
General Inspection6/8/20206/8/20206/8/2020 PASS
DetailsMichael Zawacki
Finishing up on last few homes. All are framed, one still needs some stucco.
Landscapers working at site on finished homes. Nonlandscaped lots are dirty but contained.
General Inspection5/22/20205/22/20205/22/2020 PASS
DetailsAndy J. Long
General Inspection5/7/20205/7/20205/11/2020 PASS
DetailsMichael Zawacki
Neighborhood is nearly completed. All homes are framed, no concrete work.
Landscapers on lot working on some of the completed homes. No esc issues at site.
General Inspection4/22/20204/22/20204/23/2020 PASS
DetailsMichael Zawacki
Neighborhood almost completed. Landscapers are working on homes that are completed. All homes are framed, site is clean.
General Inspection4/7/20204/7/20204/8/2020 PASS
DetailsMichael Zawacki
All lots have framed homes. Completed homes have landscaping being finished. No issues at site.
General Inspection3/23/20203/23/20203/23/2020 PART
DetailsMichael Zawacki
WIP on multiple homes.
Landscapers have some rock staged on road.
Genie lift running around causing tracking around a few homes.
General Inspection3/6/20203/6/20203/10/2020 PASS
DetailsAndy J. Long
WIP on all homes by Blackrock. No offsite trackout or discharges. Storm drains have sediment protection, trash contained. No concrete work currently. No corrections requested.
General Inspection2/20/20202/20/20202/20/2020 PART
DetailsMichael Zawacki
A few track steers and mini excavators on site causing some tracking. Building lots are relatively clean, no blowing trash.
General Inspection2/5/20202/5/20202/7/2020 PASS
DetailsAndy J. Long
No trackout or discharges leaving Warm Springs Village. SFHs permited seperately. Storm drains have sediment protection, workers parking on street and on driveways, staying off mud.
No corrections at this time
General Inspection1/21/20201/21/20201/22/2020 PASS
DetailsMichael Zawacki
All roads and sidewalks have been swept. Drain inlet bags have plenty of room. Concrete washout is nearly full. Some homes have small piles of trash but nothing out of control.
BMP Violation1/2/20201/6/20201/6/2020APASS
DetailsMichael Zawacki
Strrets and sidewalk look cleaned. Trucks dropping of loads of clean rock.
General Inspection1/2/20201/2/20201/2/2020PFAIL
DetailsMichael Zawacki
East side along boulder view needs to be cleaned. Washout is about full, missed by drivers.
Contacted Joey with Blackrock, refered me to Clint, follow up schedulled.
General Inspection12/19/201912/19/201912/19/2019PPASS
DetailsAndy J. Long
No trackout to Warm Springs. BMPs installed on the inside of site.



Correction request to Clint with Blackrock

- install rock entrance/track pad for concrete washout

Clint noted only one more week of pouring and will sweep area regularly as alternative control. Agreed that for future Blackrock washouts they will provide stabilzed access.
General Inspection12/11/201912/11/201912/11/2019 FAIL
DetailsMichael Zawacki
Message sent to Joey with Blackrock.
East side of site and around concrete washout needs to be swept.
General Inspection11/26/201911/26/201911/26/2019 PASS
DetailsMichael Zawacki
Lots of active homes at site. Concrete washout is being used. Streets and sidewalks being swept. No loose or blowing trash.
General Inspection11/11/201911/11/201911/13/2019 PASS
DetailsMichael Zawacki
East side of site is dirtier, more construction activity. Landscapers on site and some piles of backfill from recent foundation pours. Concrete washout being used. Trash is contained, no issues with it layinmg aroung or blowing, no tracking going to Warm Springs.
General Inspection10/25/201910/25/201910/25/2019 PASS
DetailsMichael Zawacki
Few stockpiles at site. WIP on many homes. Concrete washout being used. Some dirt on roads and sidewalk, nothing really bad.
General Inspection10/10/201910/10/201910/14/2019 PASS
DetailsMichael Zawacki
Multiple SFH under construction. Washout in use, trash removal company is on site. Roads are dirty near active homes, no trackout leaving site.
General Inspection9/25/20199/25/20199/25/2019 PASS
DetailsMichael Zawacki
Site is busy and crowded, WIP on multiple SFH. Some area need to be swept, will need to sweep when workers off site, to many vehicles.
Washout in use, none dumped around site.
General Inspection9/10/20199/10/20199/10/2019 PART
DetailsMichael Zawacki
Lots of activity. Site is dirty, some homes going across road to store backfill, some materials stored in road. Some lots need trash picked up. Washout is in good shape, clean, and being used.
BMP Violation8/23/20198/26/20198/30/2019PFAIL
DetailsMichael Zawacki
Washout not cleaned.
BMP Violation8/22/20198/22/20198/23/2019PFAIL
DetailsAndy J. Long
spilled/dumped concrete washou outside of washout pit.

Correction request to clean up and monitor area more regularly for mainteance. Post signs for No dumping.
General Inspection8/12/20198/12/20198/13/2019 PASS
DetailsMichael Zawacki
WIP on multiple foundations and SFHs. Washout on site. Backfill is being stored on lots by foundation work. Site is clean.
General Inspection7/26/20197/26/20197/26/2019 PASS
DetailsMichael Zawacki
Construction on multiple SFH. Site has concrete washout. No trash or debris issues at site.
General Inspection7/11/20197/11/20197/12/2019 PASS
DetailsAndy J. Long
Silt fence has been reinstalled as requested. Storm drains have maintaned sediment protection. No trackout or discharges from subdivsion. Lined concrete washout pit onsite.
General Inspection6/26/20196/26/20196/27/2019 PART
DetailsAndy J. Long
No trackout or discharges from subdivision. Utilizing lined concrete washout pit. Storm drains have sediment protection. No significant amounts of loose trash or windblown debris/dust.

Correction:
- remove damage orange silt fence and replace with sf or wattle.
- check inlets on east end of subdivision for maintenance/replacement. Some are over 50% full.
General Inspection6/10/20196/11/20196/11/2019APASS
DetailsMichael Zawacki
Silt fence along Warm Springs on east end of project, landscaping begun on west side. Every home under construction has trash box. Roads within site are clean, neighborhood washout in good shape. Some trash has blown around site.
General Inspection6/6/20196/6/20196/10/2019 CANC
DetailsAndy J. Long
General Inspection5/22/20195/22/20195/23/2019 PART
DetailsMichael Zawacki
Lots of mud on road and sidewalks within site. Nothing tracking to Warm Springs.
General Inspection5/7/20195/7/20195/7/2019 PART
DetailsMichael Zawacki
Some trucks have missed washout and have spilled in front of it, washout in good shape with plenty of room left. Some dirt on sidewalks and gutters from landscapers.
Most foundations sitting idle. No issues with blowing trash.
General Inspection4/22/20194/22/20194/22/2019 PASS
DetailsAndy J. Long
BMPs installed. Trash controlled. Lined washout provided for site. No corrections requested at this time.
General Inspection4/5/20194/5/20194/8/2019 PART
DetailsMichael Zawacki
Site is in good shape, washout being used. Some sand on sidewalks inside and on Warm spring perimeter sidewalks. Site can use some sweeping.
General Inspection3/21/20193/21/20193/22/2019 PASS
DetailsAndy J. Long
General Inspection3/6/20193/6/20193/6/2019 PASS
DetailsMichael Zawacki
Neighborhood is mostly clean. Some dirt on sidewalks, roads are clean, not much trash.
General Inspection2/19/20192/19/20192/19/2019 CANC
DetailsAndy J. Long
General Inspection2/4/20192/4/20192/6/2019PFAIL
DetailsMichael Zawacki
Pile of backfill on road. Road has layer of snow, looks very muddy underneath.
General Inspection1/25/20191/25/20191/25/2019 FAIL
DetailsMichael Zawacki
Lots of mud on roads throughout site.
General Inspection1/10/20191/10/20191/10/2019PFAIL
DetailsMichael Zawacki
Lots of mud and dirt on road and sidewalks. Some backfill is being excavated and hauled away. Washout on site and used. Inlet on spur near 2518bwarm springs has no protection. Accumulated waste from all home sites starting to add up. Area of silt fence has been ran over. Some building materials stored on road.
General Inspection12/31/201812/31/201812/31/2018 PASS
DetailsMichael Zawacki
Site currently frozen. Workers at one home.
General Inspection12/14/201812/14/201812/14/2018 PART
DetailsMichael Zawacki
Washout nearly full, some trucks dumping in front of it, some trackout, entrance needs to be repaired.
Site has areas of trackout on road and sidewalks.
General Inspection11/29/201811/29/201811/29/2018 PART
DetailsMichael Zawacki
One dump truck is driving in mud and tracking out. Washout in good condition.
General Inspection11/14/201811/14/201811/15/2018 PART
DetailsMichael Zawacki
Landscapers on site, tracking lots of dirt onto road and sidewalks. Backfill from one home on sidewalk and spilling over onto road. Community lined washout pit on site.
General Inspection10/30/201810/30/201811/1/2018 PASS
DetailsAndy J. Long
Middle section that was source of erosion and sediment runoff has had earth berm, trench, and perimeter wattle installed to prevent runoff. East end where slope is greater has silt fence. DI bags were cleaned out.

Correction request to Blackrock to get trash bins installed.
General Inspection10/12/201810/15/201810/17/2018APEND
DetailsAndy J. Long
retainment berm dug, no wattles installed. Corrections not fully complete
BMP Violation10/10/201810/12/201810/12/2018APEND
DetailsAndy J. Long
need more perimeter controls on middle section.

Earthen berm and trench dug to intercpet runoff. DI bags changed out.

STill need to install wattle and clean road from muddy excavations.
General Inspection10/8/201810/8/201810/9/2018 FAIL
DetailsAndy J. Long
Significant amount of soil being eroded into subdivision storm drain, many inlets are over whelmed and sediment bags unable to treat water. No perimeter BMPs or water diversions.

Need to determine location of discharge from large borrow ditch.

Verbal correction to Syman and BlackRock Homes
General Inspection9/21/20189/21/20189/21/2018 PASS
DetailsMichael Zawacki
Foundation for first home is completed. Neighborhood is clean, nothing leaving site.
General Inspection9/4/20189/6/20189/5/2018PPASS
DetailsAndy J. Long
No activity. SFHs are now in planning and permitting phase. No violations observed, no requests at this time
General Inspection9/3/20189/3/20189/4/2018 CANC
DetailsAndy J. Long
General Inspection8/17/20188/17/20188/17/2018 PASS
DetailsAndy J. Long
General Inspection8/2/20188/2/20188/2/2018 PASS
DetailsMichael Zawacki
No new work on development. Still prepped for homes and sitting idle.
General Inspection7/18/20187/18/20187/18/2018 PASS
DetailsMichael Zawacki
No SFH have started. Neighborhood BMPs in place.
General Inspection7/3/20187/3/20187/3/2018 PASS
DetailsMichael Zawacki
No homes started. No blowing dust, site BMPs still in place.
Site Preparation6/15/20186/18/20186/18/2018ACANC
DetailsAndy J. Long
General Inspection6/13/20186/13/20186/15/2018 CANC
DetailsAndy J. Long
General Inspection5/25/20185/29/20185/30/2018PPART
DetailsMichael Zawacki
Lots of dirt on road in site. Nothing leaving site.
General Inspection5/23/20185/23/20185/25/2018PCANC
DetailsAndy J. Long
General Inspection5/17/20185/17/20185/18/2018 PART
DetailsMichael Zawacki
Road, curb and gutters installed, no dirt leaving site.
On site has lots of runoff onto roads. Inlets on north side are surrounded by sediment and need to be maintained. Site needs to be stabalized and perimeter protected if it is going to sit inactive.
General Inspection5/2/20185/2/20185/7/2018 PASS
DetailsAndy J. Long
General Inspection4/17/20184/17/20184/17/2018 PEND
DetailsMichael Zawacki
Currently installing sidewalks and curbing. Some trackout from cement trucks leaving site.
General Inspection3/30/20183/30/20184/5/2018 PASS
DetailsAndy J. Long
No trackout, dust, or discharges. Roads not yet paved.
General Inspection3/15/20183/15/20183/15/2018 PART
DetailsMichael Zawacki
All storm water staying on site. Construction entrance/exit needs to be built.
General Inspection2/28/20182/28/20183/1/2018 CANC
DetailsAndy J. Long
General Inspection2/13/20182/13/20182/15/2018 PEND
DetailsMichael Zawacki
Running front end loaders and hauling off dirt. Some trackout to warm springs, new entrance constructed on east side of property.
General Inspection1/26/20181/29/20181/29/2018APEND
DetailsAndy J. Long
No activity. No offsite runoff. Road mix/sand has been laid for prep of road paving, but there is starting to be some opportunity for trackout from the west entrance. Will continue to monitor, but if trackout observed will request that entrance be blocked or have construction entrance installed.
General Inspection1/26/20181/26/20181/26/2018 CANC
DetailsAndy J. Long
General Inspection1/11/20181/11/20181/12/2018 PASS
DetailsAndy J. Long
No activity. No runoff observed, no trackout. Site retains stormwater well and is below Warm Springs. Road have been prepped for paving, awaiting good weather conditions.
General Inspection12/27/201712/27/201712/28/2017 PASS
DetailsMichael Zawacki
Site is on hold, frozen and covered in snow. No workers on site, hasn't been visited, snow is not tracked.
General Inspection12/12/201712/12/201712/12/2017 PASS
DetailsMichael Zawacki
Site frozen solid at time of inspection. Track Utilities is on site doing work in a trench. Rear hillside has been hydroseeded and stabalized, same as creek. Large pile of trash on back of property.
General Inspection11/24/201711/27/201711/27/2017PPASS
DetailsAndy J. Long
No sediment runoff or trackout to Warm Springs from site. Construction entrance and equipment unloading area installed to prevent mud on road.

Site grading and drainage has onsite retention. Back hill has earth berms and rock check dams to slow runoff entering the rock lined drainage channel along hill. No wattles or stabilization of back hillside, will check with Syman Company to see if it is scheduled. No violations or corrections issued.
General Inspection11/22/201711/22/201711/24/2017 CANC
DetailsAndy J. Long
General Inspection11/6/201711/6/201711/6/2017PPASS
DetailsMichael Zawacki
Storm water remaining onsite. Some trash in a pile that will need to be removed. No trackout or runoff.
General Inspection10/20/201710/20/201710/20/2017 PASS
DetailsMichael Zawacki
Site is self contained. No trackout present. Conveyance channel built along north perimeter running southwest. Will monitor for function.
General Inspection6/8/20176/8/20176/8/2017PPASS
DetailsMelissa Jannusch
WIP on excavation. No dust. water truck on site. Silt fence in good condition. No trackout. No corrections requested.
General Inspection4/10/20174/10/20174/10/2017APASS
DetailsMelissa Jannusch
Project inactive no ESC issues observed.
General Inspection4/6/20174/6/20174/6/2017PPASS
DetailsMelissa Jannusch
Contaminated soil removal complete. Grading underway. Project ok.
General Inspection3/24/20173/24/20173/24/2017PPASS
DetailsMelissa Jannusch
Contaminated soil excavation underway. A small part of the berm has been excavated. No trackout. Construction entrance is ok. Silt fence is ok. SWPPP inspections are up to date. No corrections requested.
Site Preparation3/9/20173/9/20173/9/2017PPASS
DetailsMelissa Jannusch
okay to start
Site Preparation3/7/20173/7/20173/8/2017PPASS
DetailsMelissa Jannusch
Met on site yesterday morning to discuss project and ESC requirements.

Currently just the construction entrance and sign are installed. These BMPs will be sufficient during the excavation of the lead contaminated soils while the berm is still in place. The remaining BMPs will be installed before the grading and removal of the berm are allowed to begin.

Call for additional site preparation once the additional BMPs have been installed.

No dewatering is anticipated. If dewatering is deemed necessary, a dewatering plan will need to be submitted and an inspection of the dewatering setup will be requested.