Permit Information
Permit NumberESC15-00857
StatusIssued
Name JILL JENKINS
Site Address 4190 N ARROW VILLA WAY
Project NameEyrie Canyon Sub # 9
Customer Number 
ePlanReviewNo
Description
Rough grading for a new phase of Eyrie Canyon Subdivision consisting of 17 buildable and 4 common lots on approximately 20.5 acres.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
General Inspection8/5/20208/5/20208/5/2020 PASS
DetailsMichael Zawacki
No issues on phase.
RP continues to inspect and get on builders when there is any issues.
General Inspection7/21/20207/21/20207/21/2020 PASS
DetailsMichael Zawacki
Neighborhood is clean.
General Inspection7/6/20207/6/20207/6/2020 CANC
DetailsAndy J. Long
General Inspection6/19/20206/19/20206/24/2020 PASS
DetailsMichael Zawacki
No issues on sites. Homeowners responsible for their own lots.
General Inspection6/4/20206/4/20206/8/2020 PASS
DetailsAndy J. Long
General Inspection5/20/20205/20/20205/20/2020 PASS
DetailsMichael Zawacki
No workers on site. No issues at any of lots.
No runoff from front or back.
General Inspection5/5/20205/5/20205/5/2020 PASS
DetailsMichael Zawacki
WIP on multiple homes. No issues at site. RP keeps us notified on any issues at site.
General Inspection4/20/20204/20/20204/20/2020 PASS
DetailsMichael Zawacki
Multiple homes under construction. RP still checks home construction and notifies us of any issues.
General Inspection4/3/20204/3/20204/3/2020 CANC
DetailsAndy J. Long
General Inspection3/19/20203/19/20203/19/2020 PASS
DetailsMichael Zawacki
Vacant lots are all stable. Building lots have BMPs and are the responsibility of individual builders.
General Inspection3/4/20203/4/20203/4/2020 PASS
DetailsMichael Zawacki
Siotye is clean. Building lots are taking care of their own BMPs and are clean. Washout being used. Will just need to watch trackout from form trailers and concrete trucks.
General Inspection2/18/20202/18/20202/19/2020 CANC
DetailsAndy J. Long
General Inspection2/3/20202/3/20202/4/2020 PASS
DetailsMichael Zawacki
No issues on upper phase.
Contractors on lower phase making mess, will need to sweep new section of road, tracking from washout spur.
General Inspection1/17/20201/17/20201/17/2020 PASS
DetailsMichael Zawacki
Lots still frozen, no issues at site.
General Inspection1/2/20201/2/20201/2/2020 CANC
DetailsAndy J. Long
General Inspection12/18/201912/18/201912/19/2019 PASS
DetailsMichael Zawacki
General Inspection12/3/201912/3/201912/3/2019 CANC
DetailsAndy J. Long
General Inspection11/18/201911/18/201911/21/2019 CANC
DetailsAndy J. Long
General Inspection11/1/201911/1/201911/1/2019 PASS
DetailsMichael Zawacki
Area is clean, rp repaired silt fence at bottom.
Some diirt on road at bottom from phase 10
General Inspection10/17/201910/17/201910/17/2019 PASS
DetailsMichael Zawacki
All lots that aren't being built are stable. Any issues with building lots are being directed to site RPs.
General Inspection10/2/201910/2/201910/2/2019 CANC
DetailsAndy J. Long
General Inspection9/17/20199/17/20199/17/2019 PASS
DetailsMichael Zawacki
Area is stable. No runoff or run on issues. No dirt on road. Lower storm grates are installed the wrong way, angle should be up hill.
General Inspection9/2/20199/2/20199/3/2019 PASS
DetailsMichael Zawacki
Two lots have homes under construction.
Allbuilding lotsare stable, no ssues at site.
General Inspection8/16/20198/16/20198/16/2019 PASS
DetailsMichael Zawacki
Inspected 8/15. No ESC issues.
General Inspection8/1/20198/1/20198/1/2019 CANC
DetailsAndy J. Long
General Inspection7/17/20197/17/20197/17/2019 PASS
DetailsMichael Zawacki
Bollards are still not passable.
One complaint of dust, contractor is hauling away backfill and is watering stockpile.
No dust from sewer work on new phase.
No blowing trash from any new construction.
No trackout from any active location.
General Inspection7/2/20197/2/20197/2/2019PPASS
DetailsAndy J. Long
Storm drains have sediment protection. Some minor work has commenced to begin repair and extension of Arrow Villa. No violations observed
General Inspection6/28/20196/28/20196/28/2019 CANC
DetailsAndy J. Long
General Inspection6/13/20196/13/20196/13/2019 CANC
DetailsAndy J. Long
General Inspection5/29/20195/29/20195/29/2019PPASS
DetailsMichael Zawacki
check on any hillside springs or drainage erosion on Bent Bow, 50 ft up from storm drain at Arrow Villa
No visible discharge, wet spots on road or sidewalk, or flows from hillside. No signs of road or sidewalk failure.
General Inspection5/21/20195/21/20195/21/2019 CANC
DetailsAndy J. Long
General Inspection5/6/20195/6/20195/6/2019 PASS
DetailsAndy J. Long
BMPs installed, slopes have vegetated well in phase 9. SFHs are in progress on Eyrie Way and permitted separately. Lined concrete washout pit for phase 9 homes located off Winter Camp at bottom of Eyrie Way.

Correction request:

- clean up debris and old signage on the open lot on Arrow Villa across from Goshawk and below the fire access road.
General Inspection4/19/20194/19/20194/19/2019 PASS
DetailsMichael Zawacki
Inspected 4-18. No esc issue. Work on few homes, each responsible for their own lot. Project RP keeps tabs on builders.
General Inspection4/4/20194/4/20194/4/2019 PASS
DetailsAndy J. Long
Inspected 4/2. BMPs installed, slopes are well vegetated. 3 SFHs in progress, permitted seperately. No corrrections requested.
General Inspection3/20/20193/20/20193/20/2019 CANC
DetailsAndy J. Long
General Inspection3/5/20193/5/20193/5/2019 PASS
DetailsMichael Zawacki
Met with RPs and owner on site. Repairs were made on upper end of site to contain and slow flow of water down hill. Ponds currently have capacity to absorb water. Witches hats have been replaced.
General Inspection2/18/20192/18/20192/19/2019 CANC
DetailsAndy J. Long
General Inspection2/1/20192/1/20192/1/2019 PART
DetailsMichael Zawacki
Every active lot contributing to mess. Trackout onto roads, dirty sidewalk, trash etc. No major violations.
General Inspection1/17/20191/17/20191/17/2019 PASS
DetailsAndy J. Long
General Inspection12/31/201812/31/201812/31/2018 PASS
DetailsMichael Zawacki
Street and sidewalks clean. No activity today.
General Inspection12/14/201812/14/201812/14/2018 CANC
DetailsAndy J. Long
General Inspection11/29/201811/29/201811/29/2018 PASS
DetailsAndy J. Long
General Inspection11/14/201811/14/201811/14/2018 PASS
DetailsMichael Zawacki
Two homes in phase underc onstruction. Trusses stored on road, some lumber on sidewalk. Streets are free of trackout.
General Inspection10/30/201810/30/201810/31/2018 PASS
DetailsMichael Zawacki
2 homes under construction on Eyrie Way, strrets and sidewalks show signs of being swept. Lots of lots are marked sold, expect to see more SFH construction soon.
General Inspection10/15/201810/15/201810/15/2018 CANC
DetailsAndy J. Long
General Inspection9/28/20189/28/20189/28/2018 PASS
DetailsMichael Zawacki
One lot with activity, has BMPs. No ESC issues.
General Inspection9/11/20189/13/20189/13/2018APASS
DetailsAndy J. Long
General Inspection9/11/20189/11/20189/11/2018 CANC
DetailsAndy J. Long
Conference8/27/20188/27/20188/27/2018PDONE
DetailsAndy J. Long
pre-construction safety fence and initial ESC BMP check completed, for further details, see phase 10 permit ESC18-01022

No corrections for phase 9
General Inspection8/16/20188/16/20188/16/2018 PASS
DetailsMichael Zawacki
Upper phase is clean. Some trailers and machines are on road in preparation of next phase. No new home construction has begun.
General Inspection8/1/20188/1/20188/1/2018 PASS
DetailsAndy J. Long
No discharges, trackout or dust observed. BMPs installed.

Note: no " No Trespassing" or "No construction traffic allowed" signs at the end of Arrow Villa
Conference7/11/20187/17/20187/17/2018APASS
DetailsAndy J. Long
10 AM walk through with Jill, Colin, Michael regarding phase 10 construction (to begin in August pending approvals). No issues or corrections requestd for phase 9

- reviewed grading plan and draft ESC BMP placement
- main construction entrance installation and SWPPP sign will be posted at Eyrie Way.
- large retention pond at bottom of subdivision to be cleaned out and graded during this first phase of work so that stormwater runoff can be contained onsite. Silt fence perimeter will be installed between pond and adjacent lot that borders Stewart Gulch/Sand Creek.
- storm drains on Eyrie Way will have sediment protection.
- staging area of equipment to be northeast of the stormwater pond. Will have water tank(s) onsite for dust control and soil compaction moisture.
- top soil will stockpiled at winter camp culdesac to be re-applied to graded slopes. Any long term stockpiles kept on site after grading will need to be stabilized.
- after first phase of mass grading & earthwork additional BMPs will need to be installed. (slope tracking, wattles at intervals on steep slopes, drainage controls, and check dams in any conveyances.

- as a safety control and rock barrier, straw bales will be installed below area of disturbance and above homes on the north side of Arrow Villa. It is is noted that this is not a perimeter sediment control. Preservation of hillside vegetation outside clearing limits and grading to direct water away from slope and toward future road will conducted. Additional permeter sediment controls may be required upon completion of earthwork.

Full ESC plan review has not yet been conducted and items discussed today will be included in the SWPPP narrative.
Conference7/6/20187/11/20187/11/2018ACANC
DetailsAndy J. Long
rescheduled for 7/17
General Inspection6/27/20186/27/20186/27/2018PPASS
DetailsAndy J. Long
BMPs installed. No hillside erosion or sediment runoff issues observed. 1 SFH in progress in phase, permited seperately.
General Inspection6/15/20186/15/20186/15/2018 PASS
DetailsMichael Zawacki
Most lots vacant and have cover grown over them. Neighborhood BMPs in place. No ESC issues.
Random Inspection5/31/20185/31/20185/31/2018PPASS
DetailsMichael Zawacki
Post Rain Inspection.
No runoff or BMP failure on site.
Random Inspection5/23/20185/23/20185/23/2018PPASS
DetailsMichael Zawacki
Area is clean, no ESC issues.
General Inspection5/22/20185/22/20185/22/2018 CANC
DetailsAndy J. Long
General Inspection5/7/20185/7/20185/7/2018 PASS
DetailsAndy J. Long
No new subdivsion activity. Storm drains have sediment protection, concrete washouts installed for phase 8 and phase 9. Erosion controls along Arrow Villa fire access lane are in good condition. Slopes are vegetated. SFHs are permitted seperately.

Will need to watch construction road for source of fugitive dust when in regular use, may need to implement dust controls
General Inspection4/20/20184/20/20184/20/2018 PASS
DetailsMichael Zawacki
Everything good. WIP on one home. All other lots idle.
General Inspection4/5/20184/5/20184/5/2018 PASS
DetailsMichael Zawacki
One home under construction on upper section. No ESC issues.
General Inspection3/21/20183/21/20183/21/2018PPASS
DetailsMichael Zawacki
Lots are all stable. Some sediment has accumulated around inlets at bottom of road, above where construction entrance joins paved road. Some trackout coming from concrete wash out.
General Inspection3/7/20183/7/20183/7/2018 PASS
DetailsMichael Zawacki
Lots are all stable. Some tracking around top of construction access road and road leading to washout, washout is blocked by an excavator. Lot currently building has lots of wood waste laying around.
General Inspection2/20/20182/20/20182/20/2018 PASS
DetailsMichael Zawacki
No issues observed.
General Inspection2/5/20182/5/20182/5/2018 PASS
DetailsMichael Zawacki
Neighborhood BMPs in place. No trackout from access road. No issues, one lot with construction.
General Inspection1/19/20181/19/20181/19/2018 PASS
DetailsMichael Zawacki
Upper phase is free from issues. One homesite under construction. No runoff from any of the lots. Entrance has fresh rock on it.
General Inspection1/4/20181/4/20181/4/2018 PASS
DetailsMichael Zawacki
Both ends of construction road and washout area will need their rock pads repaired when thawed. BMPs in place for neighborhood. One home is under construction.
General Inspection12/20/201712/20/201712/20/2017 PASS
DetailsAndy J. Long
No significant trackout at construction access road, but will need more heavy duty angular rock once use increases. No erosion or drainage issues along road, large retention pond located at bottom of hill to capture runoff.

1 SFH in progress on Eyrie Way. No subdivision work. Storm drain sediment controls, hillside wattles and vegetation, and drainage ditches with check dams on Arrow Villa are in good condition. No corrections requested.
General Inspection12/5/201712/5/201712/5/2017 PASS
DetailsMichael Zawacki
Work has begun on one homesite. Neighborhood BMPs in place. Access road in place, washouts installed.
General Inspection11/20/201711/20/201711/24/2017 CANC
DetailsAndy J. Long
General Inspection11/3/201711/3/201711/7/2017 PASS
DetailsMichael Zawacki
Work on buildings has not begun. Still vegetated and stable.
General Inspection10/19/201710/19/201710/19/2017 PASS
DetailsMichael Zawacki
Only access road in place. Construction entrances on both ends of road. Homesites are still all vegetated.
General Inspection9/27/20179/27/201710/4/2017 CANC
DetailsAndy J. Long
General Inspection10/4/201710/4/201710/4/2017PPASS
DetailsAndy J. Long
No construction activity at Eyrie Canyon phase #9. Temporary construction access road is complete and has rock entrance. Will monitor for future trackout issue. Receiving storm drain on Eyrie Way has sediment protection.

Hills have established vegetation, no new erosion spots or sediment runoff issues identified. Subdivision ESC team has installed new wattle check dams and silt fence line retention areas along the sides of Arrow Villa leading up to Winter Camp. This area has also had a fiber matrix erosion control application in this area.

Lined concrete washout has been provided for phase #9 SFHs, which have yet to start. No corrections requested at this time, will conduct inspection after next significant rain event.
General Inspection9/12/20179/12/20179/13/2017 CANC
DetailsAndy J. Long
Conference8/25/20178/28/20178/30/2017APEND
DetailsAndy J. Long
discuss new check dams

checks dams and other BMPs to be re-installed per SWPPP BMP details.

Will also control dust for grading activity at end of Goshawk.
General Inspection8/22/20178/22/20178/22/2017 CANC
DetailsAndy J. Long
General Inspection8/4/20178/7/20178/8/2017APASS
DetailsAndy J. Long
call jill to scheduled monday AM

Inspection of new access road and entrance at Eyrie Way. Road is road mix and should prevent trackout. RP & developer agree to monitor trackout and prevent/clean up as necessary. Storm drain inlet on Eyrie Way has had sediment filter mat installed. Drainage routes and stormwater retention/sediment basins have been installed and shall be inspected & maintained.

ESC crew to work on drainage ditches on either side of the fire access portion of Arrow Villa. Addition of top soil to encourage vegetation growth, increase soil water retention, and to direct water to roadway/gutter to storm drain drop inlets.

No violations observed at time of inspection. No ESC corrections requested.
Complaint Inspection7/28/20177/31/20178/1/2017APEND
DetailsAndy J. Long
Compaint regarding trackout on Eyrie Way.

Verbal correction request on Friday PM to RP Jill to be prepared for trackout control and street sweeping during construction of the new access road.

A street sweeper was to be ordered for Friday PM or weekend. Water truck for dust control and compaction is one reason for the trackout. Storm drain has sediment filter mat installed.

A site meeting and walk through inspection is to be scheduled to review ESC controls around road and certain areas of phase 9.
General Inspection7/17/20177/17/20177/21/2017 PASS
DetailsAndy J. Long
Inspection conducted 7/20

No grading or SFH actvity in phase #9. Storm drains have sediment filter mats installed and maintained, vegetation established on many slopes.

The construction access road for phase #9 homes was added to area disturbance for this permit in June 2016 and fees paid. Approved for Laser Leveling to professionally grade road to appease construction traffic concerns. Once installed, will inspect for additional erosion controls. Any trackout to Eyrie Way will need to be swept and and construction entrance should be installed.

No corrections requested at this time.
General Inspection6/30/20176/30/20176/30/2017 PASS
DetailsAndy J. Long
BMPs installed and maintained. NO trackout and no discharges. Hillside vegetation growing well.

Below Winter Camp a new tractor road has been cut to access basin area. Unclear what the activity is for, but it is outside the limits of Eyrie Canyon #9 and may require addition of acreage to permit and erosion & sediment controls installed. Will follow up on issue.
General Inspection6/9/20176/15/20176/19/2017PCANC
DetailsMelissa Jannusch
General Inspection6/7/20176/9/20176/9/2017ACANC
DetailsAndy J. Long
General Inspection5/26/20176/6/20176/7/2017PCANC
DetailsAndy J. Long
rescheduled for 6/9
General Inspection5/25/20175/25/20175/26/2017 CANC
DetailsAndy J. Long
General Inspection5/10/20175/10/20175/10/2017APASS
DetailsAndy J. Long
Inspection conducted on 5/9 PM. No new subdivision activity within Eyrie Canyon #9 limits. Hillside areas not on graded parcels have revegetated well.

Trackout from #9 to phase #8 has been cleaned regularly. The drainage channels on either side of Arrow Villa have had maintenance conducted on the wattle check dams and an earten berm has been installed below lots on corner of Winter Camp and Eyrie that is acting as a sediment trap. There is some erosion evident on these lots.

Storm drain inlets are protected with fiber mats.

Mudslide from graded lot down to home on Arrow Villa has started to revegetate naturally. Sod in backyard has been replaced. Will check with PW HIllside for further slope repairs that may be required, the drainage issue on the lot in question has been temporary mitigated.

Note: rill and gully erosion is occuring on the lot on Winter Camp and slope below. Recieving area is owned by developer. Slope will need repair and erosion controls installed to satisfy final ESC permit conditions.

No immediate corrections requested.
Site Preparation5/10/20175/10/20175/10/2017ACANC
DetailsAndy J. Long
data entry error, not a site prep inspection
General Inspection5/5/20175/5/20175/10/2017 CANC
DetailsAndy J. Long
General Inspection4/20/20174/20/20174/28/2017 CANC
DetailsMelissa Jannusch
General Inspection4/5/20174/5/20174/6/2017PFAIL
DetailsAndy J. Long
Corrections needed at site:

- remove accumulated sediment captured behind the check dams along Arrow Villa fire lane; provide alternate method to stabilize the drainage ditches and capture sediment
- sweeper service needed to clean up track out during hauling operation for phase 8 re-grading
- install better construction entrance stockpile area or change loading area location.
- need erosion control on the large lots at top of Arrow Villa & Winter camp. Erosion rills and sediment accumulated at downhill show need to protect this area. Recommend a hydromulch, divert run-on to this area, and install a silt fence or wattle along the bottom of sloped area.

Note: As of 4/5 mudslide from top of ridge to occupied home on Arrow Villa has not any action taken by developer, HOA or homeowner. RP stated landscaping crew is beginning 4/6
General Inspection3/30/20173/30/20173/30/2017PPEND
DetailsAndy J. Long
No subdivision activity in phase # 9. No significant sediment runoff from slopes and road shoulders observed in upper sections of subdivision. Will need to clean up accumulated sediment around strom drains.

Upper lot with temporary drainage trenches to stormwater swale has a lot of pooled stormwater. Swale/basin about to overflow which will require ther repair and regrading as conditions allow.

Siginificant open space buffer below this small pond.

Hydroseeded areas are vegetating well with grasses and various weeds
General Inspection3/22/20173/22/20173/28/2017 CANC
DetailsAndy J. Long
General Inspection3/7/20173/7/20173/7/2017PPEND
DetailsAndy J. Long
No new erosion issues, no active runoff. No construction activity or sources of trackout. Slopes and ground still very muddy and soft.

Parcel above mudslide to Arrow Villa now has drainage trenches to drain water to sediment basin to the north in EC #9, away from lot from slope to the south. Plans for slope repair were mentioned to be awaiting drier ground conditions. Conditions currently very muddy to walk or get equipment on - could cause more damage.

Corrective actions:
- work on re-installing compost wattle check dams along both sides of Arrrow Villa that are no longer in contact with bottom of channel. Remove sediment and mud from behind existing check dams.
- considering installing channel stabilization BMP , rock or turf re-enforcement matting, another application of hyroseed

General Inspection2/27/20173/2/20173/6/2017PCANC
DetailsAndy J. Long
rescheduled 3/7
General Inspection2/24/20172/24/20172/27/2017 CANC
DetailsAndy J. Long
rescheduled for Thursday 3/2 with RP for site walk through
General Inspection2/9/20172/9/20172/9/2017PPEND
DetailsAndy J. Long
follow up inspection for corrective actions

Developer excavated drainage trench on lot to direct water away from saturated and eroded slope area. Sandbags placed along back patio of home receiving mud from slide. Additional response and corrections in progress.
Complaint Inspection2/9/20172/9/20172/9/2017PFAIL
DetailsAndy J. Long
Significant mudslide due to infiltration of pooled snowmelt and rainwater on graded lot of EC#9 above homes on Arrow Villa. Slope became saturated.

Corrective:
- assist homeowner with clean up and mitigation
- work to drain the upper lots on top of this ridge, may direct to street or stormwater conveyance swale next to Arrow Villa

Investigation and corrections in progress. Follow up scheduled
General Inspection1/31/20171/31/20172/3/2017 CANC
DetailsAndy J. Long
General Inspection12/30/201612/30/20161/5/2017 PASS
DetailsAndy J. Long
snow covered and frozen conditions, no snowmelt runoff occuring. No subdivision activity. No trackout or other issues.
General Inspection12/15/201612/15/201612/15/2016PPASS
DetailsAndy J. Long
No construction activity. BMPs installed on hillside slopes. Snowmelt and runoff from project area is clear . Approved.
General Inspection11/21/201611/21/201611/25/2016 PASS
DetailsBen Livingston
no new activity, sediment has not been removed from behind waddles,
General Inspection11/2/201611/4/201611/9/2016APASS
DetailsAndy J. Long
No rencent acitivity. Too early to tell if recent hydroseed along road shoulders application has been successful. Sediment controls wattles and DI bags have been installed.

No current issues requiring correction, but recommend removing caputured sediment and hydomulch material from behind wattles at the bottom of Arrow Villa in phase 9
General Inspection10/31/201610/31/201611/2/2016 CANC
DetailsAndy J. Long
rescheduled
Random Inspection10/14/201610/14/201610/14/2016PPASS
DetailsAndy J. Long
Post precipitation inspeciton. No sediment runoff issues observed from recently hydroseeded areas. No corrective actions identified at this time.
General Inspection10/7/201610/7/201610/7/2016 PASS
DetailsAndy J. Long
Correction from last request has been completed, area around washout has been cleaned. Excess dirt and debris hauled away.

The road from Arrow Villa to Silver Crest through phase #9 is now complete. Newly installed storm drain inlets have been fitted with coir mat sediment filters. VSI recently hydroseeded distrubed road shoulders and bank slopes between terraced parcels. With precipitation the seed should grow well and has organic soil improvements and binders in the seed mixture.

Lower entrace drainage has sediment control wattles installed in intervals .

Correction recommendation:
- upper areas toward Silver Crest should have perimeter wattles strategically insstalled at potential sheet flow runoff points.

Site currently in good condition but should be inspected during the rainfall forcasted next week to identifiy potential issues.
General Inspection9/22/20169/22/20169/22/2016 PART
DetailsAndy J. Long
Road through sub is near full completion and connection to stormwater system. No trackout, dust issues or new erosion rills or runoff spots observed.

Correction:

- clean up waste stockpiles around the cement washout area.
General Inspection9/7/20169/7/20169/9/2016 CANC
DetailsAndy J. Long
General Inspection8/18/20168/23/20168/24/2016APASS
DetailsAndy J. Long
WIP on grading and compaction for road installation. Water truck also being used for fugitive dust control. Truck is causing some minor trackout from phase #9 to culdesac in phase #8. Superior will have streets swept at end of work.
General Inspection8/18/20168/18/20168/18/2016 CANC
DetailsAndy J. Long
rescheduled 8/23
Conference8/1/20168/3/20168/3/2016PPASS
DetailsAndy J. Long
Corrections requested have been completed. Streets (Arrow Villa & Goshawk) were swept and all DIs in #8 and #7 were changed out and cleaned around inlets.

Site is to be active next week with road installation. Requested that slope interuption/sediment trapping wattle be installed 75 yards up from entrance off Arrow Villa be installed on the right hand side that banks down to where the road will be.
Tracking Control8/1/20168/1/20168/1/2016PFAIL
DetailsAndy J. Long
Trackout from entrance of EC #9 to water hydrant in EC #8 was not cleaned up last week. Loose dirt and sediment on Arrow Villa and Goshawk.

Correction request:
- sweep streets
- do maintenance on inlet protection (sweep gutter aroundi inlet, change out filter bag)
- pick up any windblown trash from constructicon within project limits.

Site conference and follow up scheduled for Wednesday 8/3
General Inspection7/26/20167/26/20167/26/2016PPASS
DetailsAndy J. Long
No activity or heavy equipment on site. Sewer manholes are installed, no roads or curbing.

Need to stabilized distrubed hillsides areas with wattles and/or temporary tacifier to prevent excess runoff concentrating on the unfinished section of Arrow Villa and flowing down into existing stormwater infrastructure.

Plan to schedule site walk through with Jill and remind her of CGP and City ESC requirements to stabilize or install erosion & sediment controls in disturbed areas inactive for 2 weeks or more.
General Inspection7/7/20167/11/20167/11/2016APASS
DetailsAndy J. Long
WIP. No fugitive dust observed. Hillsides that were vegetated are undisturbed. No trackout or discharges. No corrections at this time.
General Inspection7/6/20167/6/20167/7/2016 CANC
DetailsAndy J. Long
rescheduled
Conference6/21/20166/21/20166/21/2016PPEND
DetailsAndy J. Long
Called RP to discuss use of access road on private property (owned by developer).

Correction request to forbid all non-essential construction traffic on this road unless for emergency or special load out operation. Road may be used for private access to horse stable area but not for OHV recreation.

Superior Construction to restrict use through training with employees and to block off access with barricade. Construction entrance should be via Arrow Villa only or the upper access point on Silver Crest.

Note: plan modification on 6-7-16 was to cover pre-existing temporary sediment retention pond and rock construction entrance. Added area to regulate track out and allow for alternate use only. Road has existed on this property prior to EC#9 construction.
General Inspection6/7/20166/7/20166/9/2016 PASS
DetailsAndy J. Long
Superior Construction now active onsite at Eyrie Canyon. Water truck on site and operating full time to limit dust from the tractor traffic. No plumes exiting area of construction.

Hillsides are well vegetated and crew is aware of ESC concerns at the site.

New construction entrance installed per site modifacation/variance to add access at Eyrie Way. Permit sign now also posted in this location and DI bags are installed.

RP available for review of BMPs. No corrections at this time.
General Inspection5/20/20165/20/20165/20/2016 CANC
DetailsAndy J. Long
site inspected yesteraday, no inspection today. No construction activity, no issues were observed. See Eyrie Canyon #8 permit, ESC14-01063 for inspection notes.
General Inspection5/5/20165/5/20165/5/2016 PASS
DetailsAndy J. Long
No activity at EC#9. Hillside vegetation is conitnuing to grow well.

When activity commences, need to make 2 corrections:

- ESC permit for retaining pond/construction entrance area located at Eyrie Way and Arrow Ridge
- Fix slope drain setup to carry water from future road area to the temporary retention pond.
General Inspection4/20/20164/20/20164/20/2016 PASS
DetailsAndy J. Long
No significant changes to site. Construction shall resume soon. Slopes that were hydroseeded are growing well. No new erosion or rills observed.

Note - ACHD, HOA, and developer addressing concerns on the stormwater pond that receives water from this development located on Arrow Villa & Winter Camp
General Inspection3/31/20163/31/20163/31/2016 PASS
DetailsAndy J. Long
No significant construction at site has occured. In process of getting highway district approval to finish roads. Slopes a re-vegetating well. No violations observed.

Correction to be discussed with RP next week is fixing the slope drain inlet at the end of Arrow Villa to connect runoff to the temporary retention pond/ sediment trap.
Site Preparation3/16/20163/16/20163/16/2016APASS
DetailsAndy J. Long
SWO correction requests for Eyrie Canyon #9 have been addressed by developer.

Walk through inspection of BMPs required to lift SWO conducted with Connell Development stormwater team.

1. BMPs properly re-installed, including DI sediment filter bags, earthen berm diversions, construction entrance rock stockpile now onsite, temporary retention ponds; lined concrete washout for SFHs in progress in EC phase #7 by Canyon Crest; all installed per current ESC site map of BMPs at EC #9.

2. Sidewalks and gutters are clean with no loose sediment or dirty runoff evident. No trackout onto Arrow Villa from construction area
3. Graded hillsides through out the phase were hydroseeded early March. Extra applications were put on sensitive/steep slopes. The hydroseeding from November 2015 is showing signs of establishing well and stabilizing hillsides.
4. No significant erosion rills or gullies observed due to recent rain events. No BMP failures observed. 5. Revised and updated ESC plan submitted and approved by ESC division.
6.Special Investigation fees paid.


Eyrie Canyon #9

Site now approved for construction activity and proceeding with plans to compete sewer and roads of phase 9. Work is tentatively scheduled to start in mid April.

Note: Connell Development will submit plan for staging lot at Eyrie Way to get an ESC permit for limited construction activity on this parcel, which they own.
Conference3/3/20163/3/20163/4/2016PDONE
DetailsAndy J. Long
Emailed letter outlining steps required to be completed to remove SWO. Letter was received by Jill and Colin 3/3
Complaint Inspection3/3/20163/3/20163/3/2016PDONE
DetailsAndy J. Long
Hydro-seeeding subcontractor was approved to be onsite to apply seed to the slopes and shoulder areas in phase 8 & 9. Prior to VSI (seeding company) coming on site, the developer filled in some gullies in the slopes and bermed some lots to control runoff locations.
This recent grading work has not been formerly reviewed or detailed in a grading or SWPPP plan.

Requested that all work completed this week be documented on the new SWPPP map that is required to be submitted in order to remove the SWO.

No other work not related to repairing erosion or installing BMPs (this includes the hydroseeding) is to be allowed until SWO is formerly lifted.

It was observed that water is being pumped out of Stewart Gulch creek for use in hydroseeding truck. It is unclear if this is a common or prohibited practice. There was no damage in the creek area observed, the truck is parking on the street and filling up with a hose & pump system
Conference2/22/20162/22/20162/23/2016PDONE
DetailsAndy J. Long
Contractor in process of making corrections at site. Approved to install rock constuction entrance at end of Arrow Villa. Required 2-3 angular rock. Inspect BMP and work that occured at bottom of subdivision near Stewart Gulch park.

Rock now onsite. No other activity.
Conference2/5/20162/5/20162/5/2016ADONE
DetailsAndy J. Long
Called Jill Jenkins regarding providing a compliant washout for EC phase #7 and moving the non-compliant washout from its current location at Eyrie Way and Villa Ridge.

Disclosed that case is under pending investigation and that we will be requiring a review of an updated SWPPP/ESC plan
Complaint Inspection1/25/20161/25/20161/25/2016APASS
DetailsEvan Jenkins
Emailed Videos showing direct Illicit Discharge to Stewart Gulch (Waters of the US)

--During Inspection, I was unable to locate any evidence turbid water was discharged offsite into Stewart Gulch. I appeared water came within 5ft of the bank of the stream. Will continue to monitor. Both Jenifer and Bob A. inspected the site with me
General Inspection1/8/20161/8/20161/8/2016 PEND
DetailsAndy J. Long
Stop Work Order12/21/201512/21/201512/21/2015AFAIL
DetailsEvan Jenkins
Multiple BMP violations, issues continue

Direct Illicit Discharge currently taking place into Crane Creek. Took Photos and a video for proof. All 3 ponds are connected via MS4 Piping from top pond located on Phase 8 to bottom pond.
Random Inspection12/18/201512/18/201512/18/2015PFAIL
DetailsEvan Jenkins
Significant Amount of sediment discharging off lots, onto sidewalks, curbs, gutters and drop inlets.
Need BMP Maintenance ASAP
Stop Work Order12/7/201512/7/201512/7/2015PFAIL
DetailsEvan Jenkins
SWO Issued

--No work to occur until additional BMP's are installed per manufacture spec, BMP's maintained, major cleaup of entire area and become back into compliance with BCC 8-17
Complaint Inspection12/7/201512/7/201512/7/2015AFAIL
DetailsEvan Jenkins
Significant amount of sediment discharge onto Bent Bow from Phase 9

Significant sediment flowing offsite, entering the ms4 system and ACHD stormwater ponds. No maintenance being conducted. SWO issued for both Phase 8 & 9 today
Tracking Control11/24/201511/25/201511/25/2015APASS
DetailsAndy J. Long
Trackout has been cleaned yesterday. Verified by ACHD ESC Inspector. No violations/corrections at this time.
BMP Violation11/12/201511/12/201511/12/2015PPASS
DetailsEvan Jenkins
Ensure Connell Development gets back into compliance from NOV issued on 11-10-12 (2 day allowence)

Contractor installed 650' LF or straw and compost waddles per their site plan. Construction beggining on water main break today with the use of grading, rip rap and the damaged trail will be graveled once the ground freezes to get equiptment in their. They are beggining to place straw over disturbed area for damaged areas.
BMP Violation11/10/201511/10/201511/10/2015PFAIL
DetailsEvan Jenkins
Notice of Violation to Colin Connell: for not having BMP's Installed per Site Map and for Broken water main that occured over the previous weekend, causing significant damage to the hillside and trail system.

---- Notice of Violation served to Mr. Connell for No BMP's and Water Main Break. He has 2 days from 11-10-15 at 12:30pm be get back into compliance
Complaint Inspection11/9/201511/9/201511/9/2015APART
DetailsEvan Jenkins
Complaint of a Water Main Break

Water Main break occured over the weekend. Contractor had worked with United Water to fix break and erosed areas. Those have been re-graded
Site Preparation10/15/201510/16/201510/16/2015APASS
DetailsEvan Jenkins
Jill Phone #: ###-####

Approved for Construction
Conference10/15/201510/15/201510/15/2015ADONE
DetailsEvan Jenkins
Discuss ESC/Grading Requirements with PW and Developer
--Discussed ESC expectations during construction. Mass grading expected to last 5-6 weeks. Site Prep Inspection schedualed for tomorrow
General Inspection1/16/20171/16/2017   
DetailsAndy J. Long
General Inspection12/6/201612/6/2016   
DetailsAndy J. Long